10 schemes close to CM's heart may miss deadline

DHNS
October 6, 2017

Bengaluru, Oct 6: While the ruling Congress gets bullish on promoting the government’s achievements, 10 out of 18 flagship programmes of Chief Minister Siddaramaiah - the party’s face for the upcoming Assembly polls - are unlikely to meet implementation targets before the end of his tenure.

These 18 programmes or schemes are directly monitored by the Chief Minister’s Office (CMO). Ten of them are way behind the March 2018 deadline, according to data. These programmes are facing a predicted time delay of more than 10%, which roughly means they are, at least, months behind schedule. The CMO predicts time delay for a project going by the previous pace of expenditure.

The most lagging one is the 72-km-long Namma Metro Phase-2, a project Siddaramaiah has fast-tracked in order to be completed by December 2020.

The entire project is 77% behind schedule and the government’s target of completing Reach-2 and Reach-4 by March 2018 is unlikely to be achieved. Since February 2014, the government has spent Rs 3,725 crore on the Phase-2, but has achieved only 12% physical progress.

Similarly, infrastructure works under the Hyderabad-Karnataka Region Development Board is a dismal 74% behind schedule. Out of a total 14,893 works, only 3,467 have been completed at a cost of Rs 1,500 crore.

Construction of Citizen Service Centres (Bangalore One and Karnataka One) is another area where the government has not delivered much. Only 52 centres are operational out of the targetted 102. Based on physical and financial progress, this project is 44% behind schedule.

Other flagship programmes such as Pashu Bhagya, horticulture area expansion, Basava Housing Scheme (and other housing schemes), sports infrastructure, MGNREGA and micro irrigation are 12-36% behind the March 2018 deadline. Interestingly, data reveals that some of these were implemented well initially, but have lost closer to the polls.

Only three schemes are on track. Vidyasiri, under which poor backward class students get a stipend of Rs 1,500 per month towards accommodation, has covered 3.29 lakh students against the 3.11 lakh target.

The Niranthara Jyothi Yojane (24-hour 3-phase power supply in rural areas) has already reached 15,398 villages and is 10% ahead of schedule. Similarly, the Manaswini scheme to provide Rs 500 to poor spinsters and divorced women is closer to achieving the target.

Other flagship schemes such as Anna Bhagya, new hostels, industrial infrastructure, National Rural Drinking Water Programme and Mythri are facing minor delays.

“There is now visibility and transparency, so we know where the delays are. The chief minister will hold a series of review meetings in November to push implementation,” Principal Secretary to Chief Minister L K Atheeq said. “We are confident of achieving targets,” he added.

Comments

Naveen
 - 
Friday, 6 Oct 2017

Then let us declare more new schemes

Sangeeth
 - 
Friday, 6 Oct 2017

What about the 11th scheme where he is planning to have 70% reservation quotas= for sc/st and OBCs??????

Reshma
 - 
Friday, 6 Oct 2017

When Bhaagyas get mixed up.

The Health Scheme, they provide Henda Intravenous.
Shaadi Bhaagya, is when they mixe up with Annabhagya you get Coupons for Biryani at Indira Canteen.
Anna Bhaagya, you line up for Ration, and you win a Bride.

Henda Bhaagya is one which never goes wrong, you always get Kalbatti Sarai.

Unknown
 - 
Friday, 6 Oct 2017

What is really visible physically is lagging. The scheme " Vidyasiri" claims 3.29lakh coverage instead of targeted 3.11, looks good, hope there are no bogus claims under this scheme.

Ram
 - 
Friday, 6 Oct 2017

The ruling Khangress in Karnataka should give up costly schemes that do not benefit many for cheap popularity. If the Govt. concentrates on much needed trash management, pot-hole and speed-breaker free clean smooth well lit roads with obstruction-free clear pedestrian foot-paths and other public amenity based schemes, the party need not struggle for popularity.

Indian
 - 
Friday, 6 Oct 2017

Sidha government priority should be to fill pothole in Bangalore, infact there were no roads only potholes one could see everywhere, this laxity by govt may lead to people pay hefty price !

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
June 8,2020

Mangaluru, Jun 8: Forum Fiza Mall in Mangaluru on Monday reopened for public after Ministry of Home Affairs allowed the reopening of shopping malls from June 8 with certain precautionary measures amid COVID-19 pandemic.

People visited the mall wearing masks and maintaining social distancing.

Earlier, the Union Ministry of Home Affairs (MHA) had said that religious places and places of worship for public, hotels, restaurants and other hospitality services along with shopping malls will be permitted to open from June 8.

However, these facilities will not be able to resume operations inside containment zones designated by authorities in states, said a government notification.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
coastaldigest.com news network
May 18,2020

Udupi, May 18: G Jagadeesh, Deputy Commissioner of Udupi today warned that criminal cases would be filed, if people under quarantine roam around, as they put the lives of others in risk, by coming out.

He said: "There are more than 6,000 people under quarantine in hotels, hostels, schools etc in different parts of the district. They include those who returned from other countries and other states.”

“We have allowed them to return to the district. Now I am receiving complaints that many of them are violating quarantine guidelines and venturing out. This is unacceptable.”

“As it is a risk to the whole society, severe action will be taken against the neglect and apathy of the persons under quarantine,” he said.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
February 11,2020

Mangaluru, Feb 11: BJ Puttaswamy, chairman of the State Planning Board stated that the detailed project report (DPR) to develop the Mangaluru-Karwar fisheries road at a cost of Rs 780 crores has been submitted to the state government and approval for it by the Coastal Development Authority (CDA) is pending.

Speaking to reporters here on Tuesday, he said the new developments done and in those in the future for the coastal districts.

He claimed that a feasibility report for the development of State Highway 67 has been submitted to the government.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.