10 schemes close to CM's heart may miss deadline

DHNS
October 6, 2017

Bengaluru, Oct 6: While the ruling Congress gets bullish on promoting the government’s achievements, 10 out of 18 flagship programmes of Chief Minister Siddaramaiah - the party’s face for the upcoming Assembly polls - are unlikely to meet implementation targets before the end of his tenure.

These 18 programmes or schemes are directly monitored by the Chief Minister’s Office (CMO). Ten of them are way behind the March 2018 deadline, according to data. These programmes are facing a predicted time delay of more than 10%, which roughly means they are, at least, months behind schedule. The CMO predicts time delay for a project going by the previous pace of expenditure.

The most lagging one is the 72-km-long Namma Metro Phase-2, a project Siddaramaiah has fast-tracked in order to be completed by December 2020.

The entire project is 77% behind schedule and the government’s target of completing Reach-2 and Reach-4 by March 2018 is unlikely to be achieved. Since February 2014, the government has spent Rs 3,725 crore on the Phase-2, but has achieved only 12% physical progress.

Similarly, infrastructure works under the Hyderabad-Karnataka Region Development Board is a dismal 74% behind schedule. Out of a total 14,893 works, only 3,467 have been completed at a cost of Rs 1,500 crore.

Construction of Citizen Service Centres (Bangalore One and Karnataka One) is another area where the government has not delivered much. Only 52 centres are operational out of the targetted 102. Based on physical and financial progress, this project is 44% behind schedule.

Other flagship programmes such as Pashu Bhagya, horticulture area expansion, Basava Housing Scheme (and other housing schemes), sports infrastructure, MGNREGA and micro irrigation are 12-36% behind the March 2018 deadline. Interestingly, data reveals that some of these were implemented well initially, but have lost closer to the polls.

Only three schemes are on track. Vidyasiri, under which poor backward class students get a stipend of Rs 1,500 per month towards accommodation, has covered 3.29 lakh students against the 3.11 lakh target.

The Niranthara Jyothi Yojane (24-hour 3-phase power supply in rural areas) has already reached 15,398 villages and is 10% ahead of schedule. Similarly, the Manaswini scheme to provide Rs 500 to poor spinsters and divorced women is closer to achieving the target.

Other flagship schemes such as Anna Bhagya, new hostels, industrial infrastructure, National Rural Drinking Water Programme and Mythri are facing minor delays.

“There is now visibility and transparency, so we know where the delays are. The chief minister will hold a series of review meetings in November to push implementation,” Principal Secretary to Chief Minister L K Atheeq said. “We are confident of achieving targets,” he added.

Comments

Naveen
 - 
Friday, 6 Oct 2017

Then let us declare more new schemes

Sangeeth
 - 
Friday, 6 Oct 2017

What about the 11th scheme where he is planning to have 70% reservation quotas= for sc/st and OBCs??????

Reshma
 - 
Friday, 6 Oct 2017

When Bhaagyas get mixed up.

The Health Scheme, they provide Henda Intravenous.
Shaadi Bhaagya, is when they mixe up with Annabhagya you get Coupons for Biryani at Indira Canteen.
Anna Bhaagya, you line up for Ration, and you win a Bride.

Henda Bhaagya is one which never goes wrong, you always get Kalbatti Sarai.

Unknown
 - 
Friday, 6 Oct 2017

What is really visible physically is lagging. The scheme " Vidyasiri" claims 3.29lakh coverage instead of targeted 3.11, looks good, hope there are no bogus claims under this scheme.

Ram
 - 
Friday, 6 Oct 2017

The ruling Khangress in Karnataka should give up costly schemes that do not benefit many for cheap popularity. If the Govt. concentrates on much needed trash management, pot-hole and speed-breaker free clean smooth well lit roads with obstruction-free clear pedestrian foot-paths and other public amenity based schemes, the party need not struggle for popularity.

Indian
 - 
Friday, 6 Oct 2017

Sidha government priority should be to fill pothole in Bangalore, infact there were no roads only potholes one could see everywhere, this laxity by govt may lead to people pay hefty price !

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
January 11,2020

Bantwal, Jan 11: Seven people were booked for organising protest without taking permission or intimation, police said on Saturday.

The alleged accused were identified as Nandavar Juma Masjid President Basheer, Khateeb of the Masjid Abdul Majeed Darimi, Gram Panchayath President Mohammed Shareef Nandavar, former President of Masjid Majeed, Arif Nandavar, Mustafa and Abubaker.

They have been booked for allegedly organising protest outside Nandavar Juma Masjid on Jan 10 afternoon without intimation to police or obtaining permission.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
August 7,2020

Bengaluru, Aug 7: Action will be taken against private hospitals that were violating government norms and charging exorbitant fees charges for the treatment of Covid-19 patients and suspects, said Water Resources Minister Ramesh Jarkiholi.

The government has taken action against private hospitals in Bengaluru and the same parameters would be adopted other cities, he said speaking to media persons in Belagavi on Friday.

Jarkiholi said that the government had noticed that patients were levied exorbitant charges for Covid-19 treatment. People too have complaints regarding the huge bills by these private hospitals and have demanded action.

“We are not under the obligation of any private hospital and stringent action will be taken against all erring and violating government tariffs. They will have to treat patients and follow the tariffs fixed,” he stated.

Belagavi Institute of Medical Sciences District Hospital had been directed to install CCTV cameras in Covid-19 wards and install monitors at reception to facilitate monitoring of treatment and condition of the wards. BIMS management was taken to task for not following the directive and have been given a deadline to install CCTV cameras, Jarkiholi informed.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
March 4,2020

Bengaluru, Mar 4: CM BS Yediyurappa may reconsider plans to hike taxes and curtail populist schemes in his budget on Thursday as the Centre released part of GST compensation it owes the state. Officials said the Centre released the first instalment of the bimonthly compensation for October-November amounting to Rs 2,013 crore.

"This is welcome relief as the government has been scrambling to mobilise funds," said BT Manohar, member of GST consultative committee, government of Karnataka. The second instalment of Rs 1,523 crore is also expected to be released soon.

The CM, in his seventh budget, is expected keep the focus firmly on farmers and give top priority to irrigation, agriculture and welfare schemes.

The irrigation sector is expected to land the lion's share with an allocation of at least Rs 25,000 crore, followed by agriculture. Former CM Kumaraswamy had allocated over Rs 17,000 crore for water resources.

The bulk of funds is likely to go to the Upper Krishna (UKP) and Upper Bhadra projects, as it will help backward Kalyana Karnataka and central Karnataka regions. The two are also significant political blocs. The government will also seek assistance from the Centre for the UKP project in the erstwhile Hyderabad-Karnataka region, which enjoys special status under the Constitution owing to its backwardness. P4

Yediyurappa is also expected to spell out populist schemes for the poor.

Former CM HD Kumaraswamy had allocated Rs 17,212 crore in the previous budget for water resources and Yediyurappa is likely to go well beyond that figure. "Priority will be given to irrigation and farmers," Yediyurappa had said recently. "I am making efforts to present a budget within the financial constraints."

he amounts are released once every two months, but the Centre had fallen behind on payments. PX

"There are indications that another payment will be made."

The state's optimism stems from the fact that the Centre's GST collection crossed the Rs 1 lakh crore-mark for four successive months till February.

However, the CM could still hike tax rates marginally. At a pre-budget meet on resource mobilisation where Yediyurappa is learnt to have expressed willingness to borrow funds, officials from the finance department advocated raising tax rates instead.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.