10 schemes close to CM's heart may miss deadline

DHNS
October 6, 2017

Bengaluru, Oct 6: While the ruling Congress gets bullish on promoting the government’s achievements, 10 out of 18 flagship programmes of Chief Minister Siddaramaiah - the party’s face for the upcoming Assembly polls - are unlikely to meet implementation targets before the end of his tenure.

These 18 programmes or schemes are directly monitored by the Chief Minister’s Office (CMO). Ten of them are way behind the March 2018 deadline, according to data. These programmes are facing a predicted time delay of more than 10%, which roughly means they are, at least, months behind schedule. The CMO predicts time delay for a project going by the previous pace of expenditure.

The most lagging one is the 72-km-long Namma Metro Phase-2, a project Siddaramaiah has fast-tracked in order to be completed by December 2020.

The entire project is 77% behind schedule and the government’s target of completing Reach-2 and Reach-4 by March 2018 is unlikely to be achieved. Since February 2014, the government has spent Rs 3,725 crore on the Phase-2, but has achieved only 12% physical progress.

Similarly, infrastructure works under the Hyderabad-Karnataka Region Development Board is a dismal 74% behind schedule. Out of a total 14,893 works, only 3,467 have been completed at a cost of Rs 1,500 crore.

Construction of Citizen Service Centres (Bangalore One and Karnataka One) is another area where the government has not delivered much. Only 52 centres are operational out of the targetted 102. Based on physical and financial progress, this project is 44% behind schedule.

Other flagship programmes such as Pashu Bhagya, horticulture area expansion, Basava Housing Scheme (and other housing schemes), sports infrastructure, MGNREGA and micro irrigation are 12-36% behind the March 2018 deadline. Interestingly, data reveals that some of these were implemented well initially, but have lost closer to the polls.

Only three schemes are on track. Vidyasiri, under which poor backward class students get a stipend of Rs 1,500 per month towards accommodation, has covered 3.29 lakh students against the 3.11 lakh target.

The Niranthara Jyothi Yojane (24-hour 3-phase power supply in rural areas) has already reached 15,398 villages and is 10% ahead of schedule. Similarly, the Manaswini scheme to provide Rs 500 to poor spinsters and divorced women is closer to achieving the target.

Other flagship schemes such as Anna Bhagya, new hostels, industrial infrastructure, National Rural Drinking Water Programme and Mythri are facing minor delays.

“There is now visibility and transparency, so we know where the delays are. The chief minister will hold a series of review meetings in November to push implementation,” Principal Secretary to Chief Minister L K Atheeq said. “We are confident of achieving targets,” he added.

Comments

Naveen
 - 
Friday, 6 Oct 2017

Then let us declare more new schemes

Sangeeth
 - 
Friday, 6 Oct 2017

What about the 11th scheme where he is planning to have 70% reservation quotas= for sc/st and OBCs??????

Reshma
 - 
Friday, 6 Oct 2017

When Bhaagyas get mixed up.

The Health Scheme, they provide Henda Intravenous.
Shaadi Bhaagya, is when they mixe up with Annabhagya you get Coupons for Biryani at Indira Canteen.
Anna Bhaagya, you line up for Ration, and you win a Bride.

Henda Bhaagya is one which never goes wrong, you always get Kalbatti Sarai.

Unknown
 - 
Friday, 6 Oct 2017

What is really visible physically is lagging. The scheme " Vidyasiri" claims 3.29lakh coverage instead of targeted 3.11, looks good, hope there are no bogus claims under this scheme.

Ram
 - 
Friday, 6 Oct 2017

The ruling Khangress in Karnataka should give up costly schemes that do not benefit many for cheap popularity. If the Govt. concentrates on much needed trash management, pot-hole and speed-breaker free clean smooth well lit roads with obstruction-free clear pedestrian foot-paths and other public amenity based schemes, the party need not struggle for popularity.

Indian
 - 
Friday, 6 Oct 2017

Sidha government priority should be to fill pothole in Bangalore, infact there were no roads only potholes one could see everywhere, this laxity by govt may lead to people pay hefty price !

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
June 15,2020

Bengaluru, Jun 15: Karnataka Chief Minister B S Yediyurappa on Monday laid the foundation stone for the construction of a Rs 220 crore airport project in his political bastion of Shivamogga, as he expressed confidence that it will give a boost to tourism, industries and economic activities in the region.

"The long cherished dream of people of Shivamogga about having an airport is finally becoming a reality.

The project that was planned when I was Deputy Chief Minister and Chief Minister in the past was shelved due to contractor issues and lack of interest by the governments that came later," Yediyurappa said.

Speaking at the foundation laying event for the airport, which he attended virtually via video conference, he said, now the government is once again taking up the project through infrastructure development and PWD departments.

The project to construct the well-equipped airport at Sogane in Shivamogga taluk at the cost of Rs 220 crore in about 662.38 acre land area has been initiated, he said, adding that the project will be taken up in two phases.

He expressed hope that it will be completed in a year's time.

The first phase consists of runway, taxiway, apron, approach road, peripheral road and compound wall construction, while the second phase consists of terminal building, ATC tower, fire station building, among others, a release said.

Noting that under the Udan scheme the project has been envisaged to provide affordable air travel to people, the Chief Minister expressed confidence about tourism, industries and economic activities in the region getting a boost, with the small airport coming up at Shivamogga.

He also directed officials to complete the airport work on time without compromising on the quality.

Highlighting various developmental works that is being implemented in Shivamogga, the district which is regarded as his political turf, Yediyurappa said, with the cooperation of the central government various railway projects have also been taken up in the district including Shivamogga- Shikaripura rail route.

Shikaripura is the constituency represented by the Chief Minister, while his son B Y Raghavendra represents Shimoga constituency in Lok Sabha.

Yediyurappa, who also inaugurated the divisional office of National Highway authority in the district, said a bridge project across river Sharavati at Singndur in Sagara taluk will be taken up.

Conceding that developmental work has taken a backseat due to the COVID-19 situation, the Chief Minister said the challenge is to overcome it and achieve development.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
April 9,2020

Udupi, Apr 9: Deputy Commissioner G. Jagadeesha said that criminal cases would be booked against owners of houses and sheds who were collecting rent from those, including workers, staying in rented houses.

In a statement issued here on Wednesday, Mr Jagadeesha said that to prevent the spread of COVID-19, restrictions had been imposed throughout the district under Section 144 (3) of the Criminal Procedure Code.

The administration had through an earlier order made it clear that house owners and shed owners should not collect rent from their tenants and workers for March and April.

But the administration had received complaints that some house owners and shed owners were collecting rent despite the order.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
February 27,2020

Bengaluru, Feb 27: About 60kg of unaccounted gold ornaments worth Rs. 21 crore were unearthed by officers of the Commercial Taxes Department of Karnataka Government.

The ornaments were recovered after the department conducted surprise inspections and raided business premises of wholesale jewellery dealers in Ranganatha Mansion and Sakalajee Market in Chickpet area of Bengaluru on Tuesday.

"The raid was based on information that many traders from other states visit the city and carry gold jewels without any valid documents and supply it to local jewellers without invoices," said Srikar MS Commissioner of Commercial Taxes in a statement.

The officers raided the premises of 23 jewellers and found 60 kg gold ornaments in stock which were not covered by valid documents. A penalty was levied on the undocumented ornaments.

"It is informed that the enforcement wing is keeping a close watch on the interstate movement of gold, silver and all the dealers in the state are hereby advised not to buy any goods without valid purchase invoices, added Srikar MS.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.