10 schemes close to CM's heart may miss deadline

DHNS
October 6, 2017

Bengaluru, Oct 6: While the ruling Congress gets bullish on promoting the government’s achievements, 10 out of 18 flagship programmes of Chief Minister Siddaramaiah - the party’s face for the upcoming Assembly polls - are unlikely to meet implementation targets before the end of his tenure.

These 18 programmes or schemes are directly monitored by the Chief Minister’s Office (CMO). Ten of them are way behind the March 2018 deadline, according to data. These programmes are facing a predicted time delay of more than 10%, which roughly means they are, at least, months behind schedule. The CMO predicts time delay for a project going by the previous pace of expenditure.

The most lagging one is the 72-km-long Namma Metro Phase-2, a project Siddaramaiah has fast-tracked in order to be completed by December 2020.

The entire project is 77% behind schedule and the government’s target of completing Reach-2 and Reach-4 by March 2018 is unlikely to be achieved. Since February 2014, the government has spent Rs 3,725 crore on the Phase-2, but has achieved only 12% physical progress.

Similarly, infrastructure works under the Hyderabad-Karnataka Region Development Board is a dismal 74% behind schedule. Out of a total 14,893 works, only 3,467 have been completed at a cost of Rs 1,500 crore.

Construction of Citizen Service Centres (Bangalore One and Karnataka One) is another area where the government has not delivered much. Only 52 centres are operational out of the targetted 102. Based on physical and financial progress, this project is 44% behind schedule.

Other flagship programmes such as Pashu Bhagya, horticulture area expansion, Basava Housing Scheme (and other housing schemes), sports infrastructure, MGNREGA and micro irrigation are 12-36% behind the March 2018 deadline. Interestingly, data reveals that some of these were implemented well initially, but have lost closer to the polls.

Only three schemes are on track. Vidyasiri, under which poor backward class students get a stipend of Rs 1,500 per month towards accommodation, has covered 3.29 lakh students against the 3.11 lakh target.

The Niranthara Jyothi Yojane (24-hour 3-phase power supply in rural areas) has already reached 15,398 villages and is 10% ahead of schedule. Similarly, the Manaswini scheme to provide Rs 500 to poor spinsters and divorced women is closer to achieving the target.

Other flagship schemes such as Anna Bhagya, new hostels, industrial infrastructure, National Rural Drinking Water Programme and Mythri are facing minor delays.

“There is now visibility and transparency, so we know where the delays are. The chief minister will hold a series of review meetings in November to push implementation,” Principal Secretary to Chief Minister L K Atheeq said. “We are confident of achieving targets,” he added.

Comments

Naveen
 - 
Friday, 6 Oct 2017

Then let us declare more new schemes

Sangeeth
 - 
Friday, 6 Oct 2017

What about the 11th scheme where he is planning to have 70% reservation quotas= for sc/st and OBCs??????

Reshma
 - 
Friday, 6 Oct 2017

When Bhaagyas get mixed up.

The Health Scheme, they provide Henda Intravenous.
Shaadi Bhaagya, is when they mixe up with Annabhagya you get Coupons for Biryani at Indira Canteen.
Anna Bhaagya, you line up for Ration, and you win a Bride.

Henda Bhaagya is one which never goes wrong, you always get Kalbatti Sarai.

Unknown
 - 
Friday, 6 Oct 2017

What is really visible physically is lagging. The scheme " Vidyasiri" claims 3.29lakh coverage instead of targeted 3.11, looks good, hope there are no bogus claims under this scheme.

Ram
 - 
Friday, 6 Oct 2017

The ruling Khangress in Karnataka should give up costly schemes that do not benefit many for cheap popularity. If the Govt. concentrates on much needed trash management, pot-hole and speed-breaker free clean smooth well lit roads with obstruction-free clear pedestrian foot-paths and other public amenity based schemes, the party need not struggle for popularity.

Indian
 - 
Friday, 6 Oct 2017

Sidha government priority should be to fill pothole in Bangalore, infact there were no roads only potholes one could see everywhere, this laxity by govt may lead to people pay hefty price !

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
February 17,2020

Bengaluru, Feb 17: Days after 10 MLAs were inducted in the Cabinet, Chief Minister B S Yediyurappa is likely to expand his Cabinet again as some BJP MLAs are unhappy, said BJP sources.

Several leaders including Umesh Katti, CP Yogeshwar, Raju Gowda and MP Renukacharya are miffed over the recent cabinet expansion, claim sources.

On February 6, ST Somashekar, Ramesh Laxmanrao Jarkiholi, Anand Singh, K Sudhakar, BA (Byrathi) Basavaraj, Arabail Hebbar Shivaram, Hasavanagowda C Patil, K Gopalaiah, Narayana Gowda and Shrimant Balasaheb Patil took oath as ministers.

It should be noted that many MLAs had won the by-polls on a Bharatiya Janata Party (BJP) ticket in December last year after switching loyalties from the Janata Dal (Secular) (JDS) and Congress.

In the December 5 by-polls held in 15 Assembly constituencies, the BJP had won 12, while Congress managed to bag only two. One seat was won by an Independent candidate while the JDS drew a blank.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
coastaldigest.com web desk
July 2,2020

When the black and white photos of the ‘London to Calcutta (Kolkata) bus service’ went viral on social media recently, the response of some of the netizens was “stop spreading fake news!” But, it isn’t a fake news. The late 1950s indeed offered people a lavish bus trip from London to Kolkata. 

While one of the viral images shows passengers at the Victoria Coach Station, London, boarding 'Albert', the other image show the same bus travelling through a valley. In another image the bus is stationed at a tourist spot. All these photos were captured during the bus’ maiden international journey in 1957.  

An image of the bus ticket is also making rounds on social media, that shows the route of the bus — London, Belgium, West Germany, Austria,Yugoslavia, Bulgaria, Turkey, Iran, Afghanistan, West Pakistan, India. The route in India followed Delhi, Agra, Allahabad, Banaras and finally Calcutta.

The ticket shows that a one side travel cost 145 pounds (13,644 Rupees at the present day) back then, and it was inclusive of all the luxury provided during the run.

The luxurious bus provided the facilities of reading, individual sleeping bunks, radio/taped music for parties and pleasure and fan heaters, among other things. The brochure reads, "Your complete home while you travel."

Some of the tour highlights included Banaras on the Ganges, The Taj Mahal, The Raj Path, The Rhine Valley and The Peacock Throne. Passengers reportedly got free shopping days in New Delhi, Tehran, Salzburg, Kabul, Istanbul and Vienna.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
coastaldigest.com news network
May 26,2020

Bengaluru, May 26: Karnataka chief minister BS Yediyurappa has been urged to cancel the proposed SSLC examinations in Karnataka and allow “mass-pass” for every student in the wake of covid-19 crisis. A group of intellectuals and educationists have put forth this demand.

In the letter released by educationist VP Niranjan Aradhya, said that they were listing the scientific reasons to the CM for cancellation of exams which are slated to be held from June 25 to July 4th.

In the letter, the intellectuals have elucidated a number of reasons for cancelling the upcoming exams. “There are close to 8.5 lakh students and 2.5 lakh staff involved. If we include parents who would drop their kids at the exam centre, around 30 lakh people will be involved in the process, making it a risky affair. Though the government has said that it will separate the students with fever or other ailments, will students admit to having fever? What if they consume paracetamol and come to write exams?” asks the letter. 

Added to this, the question papers have to be sent from the district and taluk centres and there may be chances of transmission.

“Even if we conduct exams, then what about the students who have failed? Every year, around 2.5 lakh students fail in the exam. Will the government conduct the supplementary exams again? The whole process of conducting exams comes at a huge cost of Rs 20 cr to Rs 25 crore. Hence, we are suggesting that the government cancels the exams and pass the entire group of student en masse,” said the letter.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.