10 schemes close to CM's heart may miss deadline

DHNS
October 6, 2017

Bengaluru, Oct 6: While the ruling Congress gets bullish on promoting the government’s achievements, 10 out of 18 flagship programmes of Chief Minister Siddaramaiah - the party’s face for the upcoming Assembly polls - are unlikely to meet implementation targets before the end of his tenure.

These 18 programmes or schemes are directly monitored by the Chief Minister’s Office (CMO). Ten of them are way behind the March 2018 deadline, according to data. These programmes are facing a predicted time delay of more than 10%, which roughly means they are, at least, months behind schedule. The CMO predicts time delay for a project going by the previous pace of expenditure.

The most lagging one is the 72-km-long Namma Metro Phase-2, a project Siddaramaiah has fast-tracked in order to be completed by December 2020.

The entire project is 77% behind schedule and the government’s target of completing Reach-2 and Reach-4 by March 2018 is unlikely to be achieved. Since February 2014, the government has spent Rs 3,725 crore on the Phase-2, but has achieved only 12% physical progress.

Similarly, infrastructure works under the Hyderabad-Karnataka Region Development Board is a dismal 74% behind schedule. Out of a total 14,893 works, only 3,467 have been completed at a cost of Rs 1,500 crore.

Construction of Citizen Service Centres (Bangalore One and Karnataka One) is another area where the government has not delivered much. Only 52 centres are operational out of the targetted 102. Based on physical and financial progress, this project is 44% behind schedule.

Other flagship programmes such as Pashu Bhagya, horticulture area expansion, Basava Housing Scheme (and other housing schemes), sports infrastructure, MGNREGA and micro irrigation are 12-36% behind the March 2018 deadline. Interestingly, data reveals that some of these were implemented well initially, but have lost closer to the polls.

Only three schemes are on track. Vidyasiri, under which poor backward class students get a stipend of Rs 1,500 per month towards accommodation, has covered 3.29 lakh students against the 3.11 lakh target.

The Niranthara Jyothi Yojane (24-hour 3-phase power supply in rural areas) has already reached 15,398 villages and is 10% ahead of schedule. Similarly, the Manaswini scheme to provide Rs 500 to poor spinsters and divorced women is closer to achieving the target.

Other flagship schemes such as Anna Bhagya, new hostels, industrial infrastructure, National Rural Drinking Water Programme and Mythri are facing minor delays.

“There is now visibility and transparency, so we know where the delays are. The chief minister will hold a series of review meetings in November to push implementation,” Principal Secretary to Chief Minister L K Atheeq said. “We are confident of achieving targets,” he added.

Comments

Naveen
 - 
Friday, 6 Oct 2017

Then let us declare more new schemes

Sangeeth
 - 
Friday, 6 Oct 2017

What about the 11th scheme where he is planning to have 70% reservation quotas= for sc/st and OBCs??????

Reshma
 - 
Friday, 6 Oct 2017

When Bhaagyas get mixed up.

The Health Scheme, they provide Henda Intravenous.
Shaadi Bhaagya, is when they mixe up with Annabhagya you get Coupons for Biryani at Indira Canteen.
Anna Bhaagya, you line up for Ration, and you win a Bride.

Henda Bhaagya is one which never goes wrong, you always get Kalbatti Sarai.

Unknown
 - 
Friday, 6 Oct 2017

What is really visible physically is lagging. The scheme " Vidyasiri" claims 3.29lakh coverage instead of targeted 3.11, looks good, hope there are no bogus claims under this scheme.

Ram
 - 
Friday, 6 Oct 2017

The ruling Khangress in Karnataka should give up costly schemes that do not benefit many for cheap popularity. If the Govt. concentrates on much needed trash management, pot-hole and speed-breaker free clean smooth well lit roads with obstruction-free clear pedestrian foot-paths and other public amenity based schemes, the party need not struggle for popularity.

Indian
 - 
Friday, 6 Oct 2017

Sidha government priority should be to fill pothole in Bangalore, infact there were no roads only potholes one could see everywhere, this laxity by govt may lead to people pay hefty price !

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
Media Release
March 11,2020

Mangalore, Mar 11: There everybody busy in hailing ‘Padmashree’ Harekala Hajabba. They wondered how an orange seller turned into an educationist with his grit and high objectives. However, the center of attraction- Harekala Hajabba was thinking how to transfer a cheque of rupees one lakh to a current account of his school!

Dakshina Kannada District Kannada and Culture Department had an interaction program with Harekala Hajabba at Ravindra Kalabhavana of University College Mangaluru on Wednesday. The department, as well as Dakshina Kannada District Bus Owners’ Association felicitated the achiever. They also honored Hajabba with a cash of rupees one lakh. Instantly, the man decided to utilize the amount for his school! 

In his address, Guruvappa N T Balepuni, who introduced Harekala Hajabba to society opined that with his simplicity, humbleness, moreover his service without any expectation, Hajabba is being respected everywhere. Though he is an illiterate, three universities have made his life as lessons for students. “He has kept around Rs 50-55 lakh, including his award money for the development of school. January 25, the day on which ‘Padmashree’ award has been declared to Hajabba is a memorable day for me too,” he added. 

Dakshina Kannada District Bus Owners’ Association President Dinram Alva and former president Jayaram Shekha opined that there is lot to learn from Hajabba and he is a model for the society. Recalling his old- harsher days, Hajabba said, “Parents should make mind to save government schools. A literate can achieve anything, he can lead the society,” he said and called upon for the communal harmony. 

Presiding over the function, Principal Dr. Uday Kumar M A said that Harekala Hajabba is best example how a pure-hearted man achieves any height, simplicity can make someone so rich. In his welcome speech District Kannada and Culture Department Deputy director Rajesh G, depicted Hajabba as ‘modern time Mahatma Gandhi’. Economics PG Coordinator Dr. Jayavantha Nayak and M.Com Coordinator Dr. Abobakkar Siddiq were present on the occasion.

 

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
May 2,2020

Udupi, May 2: All the 18 people who were advised self-quarantine in connection with the Thekkatte petrol bunk incident have been tested negative, however, they were asked to continue the 14-day quarantine, said DHO Sudhirchandra Suda on Saturday.

the petrol bunk at Thekkatte was sealed after a Covid infected person had food and took bath at the petrol bunk, while he was travelling from Mumbai to Mandya.

The employees and the owner of the petrol bunk along with the six employees at Sasthana toll gate were asked to quarantine themselves for 14 days.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
July 11,2020

Bengaluru, Jul 11: Karantaka Congress chief DK Shivakumar on Friday raised questions over claims that Rewa Ultra Mega Solar Power Project Madhya Pradesh was "largest in Asia" and said a 2000 MW had been built in the state.

"BJP central government is claiming today that it inaugurated Asia's largest solar plant of 750 MW at Rewa, MP. What then is the 2000 MW Solar Plant in Pavagada, Karnataka which was built in just 3 years by Karnataka Congress government and has been operational since 2018?" Shivakumar said in a tweet.

The Congress leader further said that the most unique thing about the solar project set up in Karnataka was that the farmers were being paid yearly rents for the land upon which it was constructed as it had been leased and not purchased from them, helping them retain ownership.

"The unique thing about the 2000 MW Pavagada Mega Solar Park was that not a single acre of land was acquired from the farmers. All 13,000 acres have been leased from the farmers who are being given yearly rent. Karnataka model of renewable energy was accepted as the best in India," he said.

"Union power minister must answer as to how the Central Government can claim that the Rewa Solar Park (750 MW) opened today is Asia's largest when clearly the Pavagada Park in Karnataka is much larger (2000 MW) and was opened two years back!" he said.

Prime Minister Narendra Modi dedicated Rewa Ultra Mega Solar Power Project to the nation on Friday. 

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.