10 schemes close to CM's heart may miss deadline

DHNS
October 6, 2017

Bengaluru, Oct 6: While the ruling Congress gets bullish on promoting the government’s achievements, 10 out of 18 flagship programmes of Chief Minister Siddaramaiah - the party’s face for the upcoming Assembly polls - are unlikely to meet implementation targets before the end of his tenure.

These 18 programmes or schemes are directly monitored by the Chief Minister’s Office (CMO). Ten of them are way behind the March 2018 deadline, according to data. These programmes are facing a predicted time delay of more than 10%, which roughly means they are, at least, months behind schedule. The CMO predicts time delay for a project going by the previous pace of expenditure.

The most lagging one is the 72-km-long Namma Metro Phase-2, a project Siddaramaiah has fast-tracked in order to be completed by December 2020.

The entire project is 77% behind schedule and the government’s target of completing Reach-2 and Reach-4 by March 2018 is unlikely to be achieved. Since February 2014, the government has spent Rs 3,725 crore on the Phase-2, but has achieved only 12% physical progress.

Similarly, infrastructure works under the Hyderabad-Karnataka Region Development Board is a dismal 74% behind schedule. Out of a total 14,893 works, only 3,467 have been completed at a cost of Rs 1,500 crore.

Construction of Citizen Service Centres (Bangalore One and Karnataka One) is another area where the government has not delivered much. Only 52 centres are operational out of the targetted 102. Based on physical and financial progress, this project is 44% behind schedule.

Other flagship programmes such as Pashu Bhagya, horticulture area expansion, Basava Housing Scheme (and other housing schemes), sports infrastructure, MGNREGA and micro irrigation are 12-36% behind the March 2018 deadline. Interestingly, data reveals that some of these were implemented well initially, but have lost closer to the polls.

Only three schemes are on track. Vidyasiri, under which poor backward class students get a stipend of Rs 1,500 per month towards accommodation, has covered 3.29 lakh students against the 3.11 lakh target.

The Niranthara Jyothi Yojane (24-hour 3-phase power supply in rural areas) has already reached 15,398 villages and is 10% ahead of schedule. Similarly, the Manaswini scheme to provide Rs 500 to poor spinsters and divorced women is closer to achieving the target.

Other flagship schemes such as Anna Bhagya, new hostels, industrial infrastructure, National Rural Drinking Water Programme and Mythri are facing minor delays.

“There is now visibility and transparency, so we know where the delays are. The chief minister will hold a series of review meetings in November to push implementation,” Principal Secretary to Chief Minister L K Atheeq said. “We are confident of achieving targets,” he added.

Comments

Naveen
 - 
Friday, 6 Oct 2017

Then let us declare more new schemes

Sangeeth
 - 
Friday, 6 Oct 2017

What about the 11th scheme where he is planning to have 70% reservation quotas= for sc/st and OBCs??????

Reshma
 - 
Friday, 6 Oct 2017

When Bhaagyas get mixed up.

The Health Scheme, they provide Henda Intravenous.
Shaadi Bhaagya, is when they mixe up with Annabhagya you get Coupons for Biryani at Indira Canteen.
Anna Bhaagya, you line up for Ration, and you win a Bride.

Henda Bhaagya is one which never goes wrong, you always get Kalbatti Sarai.

Unknown
 - 
Friday, 6 Oct 2017

What is really visible physically is lagging. The scheme " Vidyasiri" claims 3.29lakh coverage instead of targeted 3.11, looks good, hope there are no bogus claims under this scheme.

Ram
 - 
Friday, 6 Oct 2017

The ruling Khangress in Karnataka should give up costly schemes that do not benefit many for cheap popularity. If the Govt. concentrates on much needed trash management, pot-hole and speed-breaker free clean smooth well lit roads with obstruction-free clear pedestrian foot-paths and other public amenity based schemes, the party need not struggle for popularity.

Indian
 - 
Friday, 6 Oct 2017

Sidha government priority should be to fill pothole in Bangalore, infact there were no roads only potholes one could see everywhere, this laxity by govt may lead to people pay hefty price !

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
January 6,2020

Bengaluru, Jan 6: Chief minister BS Yediyurappa has plenty on his plate ahead of the 2020-21 state budget to be presented on March 5 what with the economic slowdown and a sizeable shortfall in revenue, but the biggest worry is the uncertainty surrounding Goods and Services Tax (GST) compensation from the Centre.

There is also uncertainty over the state’s share under devolution of funds as per the 14th Finance Commission recommendation.

Finance department officials say that while Rs 3,500 crore is expected as GST compensation for every two months, the devolution of funds would have yielded about Rs 7,000 crore for the current fiscal. But the economic slowdown appears to have hit the Centre’s finances and is likely to impact the state’s share of funds.

“The GST payment for August-September came only in December and we are unsure how much we will get for October-November and December-January,” an official said. Estimates suggest the state’s share under devolution of funds could be reduced by half.

At a meeting of finance department officials last week, Yediyurappa is said to have admitted that unlike those states where non-BJP parties are in power — they have threatened agitations and court cases — the government cannot go “against” Prime Minister Narendra Modi’s regime.

Instead, Yediyurappa has urged senior IAS finance department officials to lobby for funds with their counterparts in New Delhi. On his part, Yediyurappa is said to have already written to Modi and finance minister Nirmala Sitharaman to at least release the state’s share of GST compensation for the current calendar year of 2019. He is planning to personally meet the PM in Delhi to push the state’s case.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
April 17,2020

Kalaburagi, Apr 17: Hundreds of people participated in the Siddhalingeswara temple chariot festival in Chitapur village on Thursday, violating the lockdown orders.

"Today at 6.30 am, around 100-150 people had come near Siddalingeshwara temple for about 20 mintues and took part in chariot pulling procession," Superintendent of Police Lada Martin said.

A case has been registered against 20 people and further investigation is going to ascertain more details related to the religious gathering.
Meanwhile, a sub-inspector has been suspended.

Thirty-six cases of coronavirus were reported in Karnataka on Thursday, taking the state's tally to 315.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
April 19,2020

Mangaluru, Apr 19: District-in-charge Minister Kota Srinivas Poojary said that Rs 2000 each has been deposited in the bank accounts of 6,122 construction workers, who are registered with the labour department in the Dakshina Kannada district. The amount will be deposited in the accounts of other registered construction workers at the earliest.

The state government had announced Rs 2000 to construction labourers who are registered and have lost their livelihood due to the on-going nationwide lockdown to curb the spread of the coronavirus. The curbs, which were imposed on March 24, have been extended till May 3. "The labourers were reeling under hardship after construction activities came to a halt," said the Minister.

Supply food

Local bodies should make arrangements to supply food for stranded labourers, destitutes and beggars in all the ULBs in Dakshina Kannada district, Poojary said. 

"No one should starve during the lockdown period. All the ULBs should identify destitutes, migrant labourers in their jurisdiction and arrange food for them. In case of necessity, the help of NGOs can also be taken," he added
The minister announced that Asha workers and health workers would collect information on people's health by visiting the houses in the district and submit a report within 10 days.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.