Major blow to Adani's Udupi power project; NGT declares clearances granted to set up plant are illegal

coastaldigest.com news network
March 16, 2019

Udupi, Mar 16: In a major blow to Adani's Udupi Power Plant project at Yellur village of Udupi district, the Principal Bench of the National Green Tribunal declared on 14" March 2019 that all the clearances granted to set up the power plant are illegal. It has also ordered the suspension of the Environmental Clearance dated 1.08.2017 granted to expand the plant by addition of 2x800MW units to raise ultimate capacity to 2800MW. The Tribunal invoked the "Polluter Pays" principle and appointed a committee of experts to ascertain the damages to the crops and the environment in general of the area. It has directed the Company to pay 5 crores as an interim environmental compensation to CPCB who will also be the Nodal agency to study the damages caused. It has also ordered the Company to pay Rs. 1 lakh as cost to the Petitioners.

The Tribunal found that genuinely serious issues raised by the villagers and the Applicants had not been given the due attention it observed by all concerned including the Government. The fact that multitudes of disputes and litigations relating to the project had been instituted bears witness to the fact that all was not well. Environmental clearance dated 20.03.1997 had been granted without following the due process statutorily prescribed and mandatorily required to be followed. Extension of the validity period of the EC had been granted on 16.04.2002 at the request of the project proponent as work could not be commenced within the 5 years' period stipulated in the EC. This is without authority of law. On 05.10.2004 the EC was cancelled by the Ministry as the project proponent had still not commenced with the work of the project. This order of cancellation was recalled vide a personal letter dated 31.01.2005 by the Director MOEF under questionable circumstances at the request of the project proponent.

The Tribunal pointed out that the procedures laid down under the EIA Notifications are not mere formalities to be followed but have been prescribed to ensure that the environment is duly protected while taking up a project keeping in view the Precautionary Principle and the principle of Sustainable Development. The fact that the procedures prescribed in the Notification were not at all followed except few parts of it, lead it to reasonably conclude that there has been damage caused to the environment for which consequences have fallen on the people in terms of healtn, decline in the agricultural productivity and, therefore, their livelihood, degradation of natural habitat of birds and animals, etc.

Tribunal took a serious note of the study carried out on "Environmental Profile and People's Livelihood aspects in the vicinity of Coal Based Thermal Power Plant at Yellur Panchayat, Udupi District" by a group of Scientists as CES Technical Report 126 dated April 2012 published by the Energy & Wetland Research Group, Centre for Ecological Sciences, Indian Institute of Science, Bangalore, has made alarming observations in respect of the project area during field investigations. It has been observed that mismanagement of the environment was evident from the contamination of the water (surface and ground), soil and air apart from the impaired functional aspects of the biotic elements. This was deduced from the reduced productivity of grains, jasmine flower and horticultural produce, reproductive ability of livestock, poultry animals, etc. There was dust on the leaves during the dry seasons which induced phyto-toxicity leading to poor pollination and hence reduced productivity. There was reduction in the population of pollinators. Stunted growth of saplings and enhanced respiratory diseases, etc. were noticed caused by release of saline mist from the cooling towers of the plant which is locally dispersed by the wind even up to 2 kms.

The Tribunal found the conduct of the MoEF&CC in the entire episode does not appear to be above board. The Tribunal expresses grave anguish and concern which in its view ought to be corrected and left it upon the MoEF&CC to deal with this aspect as their wisdom may dictate.

The Tribunal observed that justifiably, therefore, the directions would be called for to remove the plant and order for restoration of the area and the environment. However, considering the facts and circumstances, the lapse of time and the fait accompli situation that has arisen, we are of the view that the interest of public will not be served in passing such order. The need of the hour is to explore such measures and steps that would mitigate the harm already caused in addition to ensuring that the plant operates strictly within the environmental norms. It has thus invoked the "Polluter Pays" principle under Section 20 of the National Green Tribunal Act, 2010 and hold M/s. Udupi Power Corporation Ltd., the Respondent No. 5, project proponent, liable to pay Environmental Compensation which shall bg assessed by a Committee of Experts. It has constituted a Committee comprising of- 1. Senior Scientist, CPCB. 2. Senior Representative, IIT Chennai. 3. Senior Scientist, IIT Bangalore. CPCB shall be the nodal agency to coordinate amongst the Members for taking up the task.

The Committee shall assess the environmental damage on account of the environmental violations and submit its report within three months. Awaiting such report, it directed UPCL to pay an interim Environmental Compensation of k5 crores with the CPCB. The interim compensation would be subject to assessment of final damages by the Committee of Experts. This amount shall be deposited within a period of one month from hence. The CPCB, in the meanwhile, shall utilize the interim compensation for restitution and remedial works for restitution of the environment including the possible plight of the people affected by the plant. It has made it clear that this amount shall be distinct from the other obligations of UPCL under the Corporate Social Responsibility (CSR) or other obligations.

The project was challenged as early as in 2004 by the Samithi before the then National Environmental Appellate Authority (NEAA), New Delhi. The appeal was dismissed by the sole non-judicial adjudicator who was formerly the Secretary, MOEF responsible earlier for the grant of the very Environmental Clearance. Aggrieved by the decision, the Samithi filed WP before the Karnataka High Court in 2005. Bellibettu Alade Devasthana and CSI St. Luke's Church also filed separate Writ Petitions before the High Court. The cases were transferred to the National Green Tribunal South Zone, Chennai in 2012 under the Supreme Court order. Due to the lack of Judges in Zonal Tribunal at Chennai the cases were finally heard by the Principal Bench at New Delhi and the judgement was released on 14th March 2019. The State of Karnataka actually does not need power from the plant and Govt has either stopped or considerably reduced receiving the supply from UPCL. The Energy Dept website show that as on 31.07.2018 the total generation of power from various sources has increased to 27,176.43 MW out of which 4,713.26 MW is Wind Energy and 5,172.72 MW is Solar among others. The website also shows that the available potential of the Renewable Energy totals to 86,792MW of which Wind Energy is 55,857MW and Solar 24,700MW. With such RE potential the killer coal-based power plants are not at all required in the State leave alone in the sensitive Ecologically Coastal Zone.

As such the State Govt is required to issue directions to UPCL to shut it down and shift it to another place perhaps another country like Bangladesh. It has also come to the knowledge of the Samithi that UPCL is now planning new Transmission Lines to supply power to other State perhaps through the grid at Kerala. It would only mean that we would be used as sacrificial lambs for the Company and this will not be acceptable.

Comments

jaleel
 - 
Monday, 18 Mar 2019

Now even the plant is shut, it's the public who are at lose. Govt provided public money to Mota bhai to set up this plant. Coorporate sect always play with public life, money. They keep people busy in fake and unwanted issues and politicians prepare grounds for all these nuisance. Tuticorn in Tamilnadu and likewise many examples are in front of us. This will happen again and again We are fools really. At least for the sake of our next generation we should start thinking like a man not like donkey  

 

 

 

 

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
August 3,2020

Bengaluru, Aug 3: A building of Bengaluru's civic body, Bruhat Bengaluru Mahanagara Palike (BBMP), on Broadway Road in Shivajinagar, is being developed into a COVID dedicated hospital with 200 beds, Karnataka Medical Education Minister K Sudhakar said on Sunday.

The hospital will be functional in two weeks, said Sudhakar.

"BBMP building in Broadway Road is converted into Covid hospital. Setting up of infrastructure like beds, ventilators, oxygen etc is underway.

All necessary staff for this hospital including doctors, nurses and paramedical staff have been already deployed and the work is on fast track," Sudhakar tweeted.

He also thanked Infosys foundation and it's Chairperson Sudha Murthy for immediately responding to government's request and providing infrastructure for this hospital.

In a tweet, Sudhakar thanked the doctors for their service to combat COVID-19 in the state.
"These doctors have extended helping hand in these corona times without any expectations. I salute their spirit of service and professionalism," Minister said in a tweet.

According to the Union Health Ministry, there are 1,34,819 COVID-19 cases in the state. 

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
March 13,2020

Bengaluru, Mar 13: This year, schoolchildren will have a longer summer vacation starting early, thanks to the new coronavirus onslaught. Primary and Secondary Education Minister Suresh Kumar on Thursday announced that schools in Bengaluru Urban and Rural districts will be closed for vacation from Friday.

Classes from LKG to sixth standard will closed for vacations till the schools reopen in June, while students of classes 7-9 will have ‘study holidays’ until their examinations commence (as scheduled by their respective schools). Their summer vacations will begin with the completion of their examinations.

Class 10 students will have their examinations according to the dates scheduled earlier.

“Let us not treat this as a panic reaction or something to cause a scare. This measure is taken as a precaution. A lot of parents were worried about their children. We have already announced the closure of schools from nursery to sixth standards. Now, we are declaring official holidays upto sixth standard. Students of standards 1-6 will all be promoted based on their formative assessment,” said Kumar adding, “no student will be detained in those classes.”

With respect to seventh, eighth and ninth standards, the schools will be closed for study holidays and students will have to return to write their examinations.“We will not interfere in the examination schedules of CBSE and ICSC schools. However, state syllabus schools have to finish their examinations before March 23”, Public Instruction Commissioner KG Jagadeesh said.Just a couple of papers of the PU examinations are left after which their holidays will begin.

Exam timetable not changed

Miscreants are spreading rumours that SSLC examination dates are changed because of the new coronavirus outbreak. However, Karnataka Secondary Education Examination Board director V Sumangala categorically said the examinations will be held from March 27  to April 9 as scheduled earlier.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
July 1,2020

Mumbai, Jul 1: The Maharashtra government will set up a Marathi medium college in Kolhapur for the Marathi- speaking people residing in the border areas of Karnataka, a minister said on Tuesday.

Higher and technical education minister Uday Samant, in a statement here, said the decision has been taken with a view to cater to the educational needs of the Marathi-speaking population residing in the neighbouring state.

He said the new state-run college will be a sub-centre of the Shivaji University at Kolhapur.

The Kolhapur district collector will provide a five- acre plot for the proposed college following which all necessary official permissions will be given, Samant said.

The college will start functioning from the next academic year, the release said.

Acommittee headed by Shivaji University vice- chancellor Nitin Karmalkarwill work out the modalities for establishing the educational institute, it added.

The border areas of Karnataka have a sizeable Marathi- speaking population.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.