Udupi, Mar 16: In a major blow to Adani's Udupi Power Plant project at Yellur village of Udupi district, the Principal Bench of the National Green Tribunal declared on 14" March 2019 that all the clearances granted to set up the power plant are illegal. It has also ordered the suspension of the Environmental Clearance dated 1.08.2017 granted to expand the plant by addition of 2x800MW units to raise ultimate capacity to 2800MW. The Tribunal invoked the "Polluter Pays" principle and appointed a committee of experts to ascertain the damages to the crops and the environment in general of the area. It has directed the Company to pay 5 crores as an interim environmental compensation to CPCB who will also be the Nodal agency to study the damages caused. It has also ordered the Company to pay Rs. 1 lakh as cost to the Petitioners.

The Tribunal found that genuinely serious issues raised by the villagers and the Applicants had not been given the due attention it observed by all concerned including the Government. The fact that multitudes of disputes and litigations relating to the project had been instituted bears witness to the fact that all was not well. Environmental clearance dated 20.03.1997 had been granted without following the due process statutorily prescribed and mandatorily required to be followed. Extension of the validity period of the EC had been granted on 16.04.2002 at the request of the project proponent as work could not be commenced within the 5 years' period stipulated in the EC. This is without authority of law. On 05.10.2004 the EC was cancelled by the Ministry as the project proponent had still not commenced with the work of the project. This order of cancellation was recalled vide a personal letter dated 31.01.2005 by the Director MOEF under questionable circumstances at the request of the project proponent.

The Tribunal pointed out that the procedures laid down under the EIA Notifications are not mere formalities to be followed but have been prescribed to ensure that the environment is duly protected while taking up a project keeping in view the Precautionary Principle and the principle of Sustainable Development. The fact that the procedures prescribed in the Notification were not at all followed except few parts of it, lead it to reasonably conclude that there has been damage caused to the environment for which consequences have fallen on the people in terms of healtn, decline in the agricultural productivity and, therefore, their livelihood, degradation of natural habitat of birds and animals, etc.

Tribunal took a serious note of the study carried out on "Environmental Profile and People's Livelihood aspects in the vicinity of Coal Based Thermal Power Plant at Yellur Panchayat, Udupi District" by a group of Scientists as CES Technical Report 126 dated April 2012 published by the Energy & Wetland Research Group, Centre for Ecological Sciences, Indian Institute of Science, Bangalore, has made alarming observations in respect of the project area during field investigations. It has been observed that mismanagement of the environment was evident from the contamination of the water (surface and ground), soil and air apart from the impaired functional aspects of the biotic elements. This was deduced from the reduced productivity of grains, jasmine flower and horticultural produce, reproductive ability of livestock, poultry animals, etc. There was dust on the leaves during the dry seasons which induced phyto-toxicity leading to poor pollination and hence reduced productivity. There was reduction in the population of pollinators. Stunted growth of saplings and enhanced respiratory diseases, etc. were noticed caused by release of saline mist from the cooling towers of the plant which is locally dispersed by the wind even up to 2 kms.

The Tribunal found the conduct of the MoEF&CC in the entire episode does not appear to be above board. The Tribunal expresses grave anguish and concern which in its view ought to be corrected and left it upon the MoEF&CC to deal with this aspect as their wisdom may dictate.

The Tribunal observed that justifiably, therefore, the directions would be called for to remove the plant and order for restoration of the area and the environment. However, considering the facts and circumstances, the lapse of time and the fait accompli situation that has arisen, we are of the view that the interest of public will not be served in passing such order. The need of the hour is to explore such measures and steps that would mitigate the harm already caused in addition to ensuring that the plant operates strictly within the environmental norms. It has thus invoked the "Polluter Pays" principle under Section 20 of the National Green Tribunal Act, 2010 and hold M/s. Udupi Power Corporation Ltd., the Respondent No. 5, project proponent, liable to pay Environmental Compensation which shall bg assessed by a Committee of Experts. It has constituted a Committee comprising of- 1. Senior Scientist, CPCB. 2. Senior Representative, IIT Chennai. 3. Senior Scientist, IIT Bangalore. CPCB shall be the nodal agency to coordinate amongst the Members for taking up the task.

The Committee shall assess the environmental damage on account of the environmental violations and submit its report within three months. Awaiting such report, it directed UPCL to pay an interim Environmental Compensation of k5 crores with the CPCB. The interim compensation would be subject to assessment of final damages by the Committee of Experts. This amount shall be deposited within a period of one month from hence. The CPCB, in the meanwhile, shall utilize the interim compensation for restitution and remedial works for restitution of the environment including the possible plight of the people affected by the plant. It has made it clear that this amount shall be distinct from the other obligations of UPCL under the Corporate Social Responsibility (CSR) or other obligations.

The project was challenged as early as in 2004 by the Samithi before the then National Environmental Appellate Authority (NEAA), New Delhi. The appeal was dismissed by the sole non-judicial adjudicator who was formerly the Secretary, MOEF responsible earlier for the grant of the very Environmental Clearance. Aggrieved by the decision, the Samithi filed WP before the Karnataka High Court in 2005. Bellibettu Alade Devasthana and CSI St. Luke's Church also filed separate Writ Petitions before the High Court. The cases were transferred to the National Green Tribunal South Zone, Chennai in 2012 under the Supreme Court order. Due to the lack of Judges in Zonal Tribunal at Chennai the cases were finally heard by the Principal Bench at New Delhi and the judgement was released on 14th March 2019. The State of Karnataka actually does not need power from the plant and Govt has either stopped or considerably reduced receiving the supply from UPCL. The Energy Dept website show that as on 31.07.2018 the total generation of power from various sources has increased to 27,176.43 MW out of which 4,713.26 MW is Wind Energy and 5,172.72 MW is Solar among others. The website also shows that the available potential of the Renewable Energy totals to 86,792MW of which Wind Energy is 55,857MW and Solar 24,700MW. With such RE potential the killer coal-based power plants are not at all required in the State leave alone in the sensitive Ecologically Coastal Zone.

As such the State Govt is required to issue directions to UPCL to shut it down and shift it to another place perhaps another country like Bangladesh. It has also come to the knowledge of the Samithi that UPCL is now planning new Transmission Lines to supply power to other State perhaps through the grid at Kerala. It would only mean that we would be used as sacrificial lambs for the Company and this will not be acceptable.

Comments

jaleel
 - 
Monday, 18 Mar 2019

Now even the plant is shut, it's the public who are at lose. Govt provided public money to Mota bhai to set up this plant. Coorporate sect always play with public life, money. They keep people busy in fake and unwanted issues and politicians prepare grounds for all these nuisance. Tuticorn in Tamilnadu and likewise many examples are in front of us. This will happen again and again We are fools really. At least for the sake of our next generation we should start thinking like a man not like donkey  

 

 

 

 

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
April 27,2020

Madikeri, Apr 27: Four labourers, who were travelling to Kerala via Makutta on foot, were stopped by Karnataka Forest Department officials and handed over to police.

Police said on Monday that the labourers identified as Anish, Radhakrishna, Shrinil and Prabhakar, who were working in the Coffee plantations in Chembellur and Ontiyangadi. As the roads to Kerala were sealed following lockdown, they were held up in the district.

The forest guards, who spotted them walking through the forest area, brought them back to the town as per the directions of the higher officials last evening. DCF Shivashankar, ACF Konerira Roshni and Ranger Arun Kumar were present.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
January 8,2020

Bengaluru, Jan 8: The second instalment of flood relief funds from the Centre, announced on Monday, has left BS Yediyurappa less than cheerful, with the chief minister insisting that it is barely adequate. The CM on Tuesday said he will urge the Union government to release more.

On Monday, the Centre announced it will release Rs 669.8 crore in addition to the Rs 1,200 crore it had released earlier towards flood relief and rehabilitation. The total sum is a small fraction of the loss, which the government pegged at a staggering Rs 38,000 crore.

“The Centre has released assistance in two instalments so far, but it is inadequate given the magnitude of the damage. I will request for more funds and I am confident the Centre will oblige,” Yediyurappa told reporters.

When Prime Minister Narendra Modi had visited the state last week, Yediyurappa had urged him — even openly at a function — to release funds. This followed several pleas over the past four months, which barely drew a response from the Centre. Now, the CM himself suggests it’s barely a drop in the ocean.

The opposition has been criticizing both Yediyurappa and the Centre for their handling of the situation and on Tuesday, leader of the opposition Siddaramaiah of the Congress criticised the CM for “misguiding people” on the sum released by the Centre.

Siddaramaiah tweeted, “Reports from State govt officials say only Rs 669 cr of addl funds are released in 2nd instalment as opposed to the claim of Rs 1,870 cr by Karnataka BJP leaders. At a time when manufacturing industries are closing, BJP’s fake news factory is running at full potential ".

In another tweet, he said, “Moved by the plea of chief minister, Yediyurappa, Prime Minister Narendra Modi released an additional Rs 669.8 crore, taking the total amount to Rs 1,869.8 crore. BJP leaders, who are devotees of the god of lies, attempts to depict the total relief amount as 1200+1869.85 = Rs 3,069 cr is ridiculous.”

A high-level committee chaired by Union home minister Amit Shah had sanctioned the National Disaster Response Fund (NDRF) funds on Monday. While the Press Information Bureau claimed Rs 1,869 crore was approved on Monday, state government officials clarified that the figure included the Rs 1,200 crore released in October.

Meanwhile, sources say the two instalments is all the assistance the state can expect from the Centre towards flood relief. Sources say the Rs 1,870 crore is roughly 60% of the funding — Rs 3,000 cr— which was supposed to be allocated for Karnataka, based on an inter-ministerial team’s assessment of losses in the state.

“Compared to other states for the same period, Karnataka has received the highest amount in flood relief. We cannot expect more,” said a revenue department official, who said the government will not approach the Centre for a special package.

However, revenue minister R Ashoka said the state will pitch for the entire Rs 3,000 crore. “The state government will pursue the matter with the Centre until it releases the entire Rs 3,000 crore. The state government will cover the remainder of the Rs 38,000 crore loss. We will not go back on our word,” Ashoka said. Incidentally, the state has spent about Rs 6,000 crore on relief and rehabilitation so far.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
May 1,2020

Bengaluru, May 1: Karnataka has reported 11 new cases of coronavirus, taking the State's count to 576, informed the Health Department on Friday.

Out of the total COVID-19 cases found in the State, 235 people have been discharged and 22 people have died.

"11 new COVID-19 cases have been confirmed in Karnataka from April 30, 5 pm till noon today, taking the total number of cases to 576, which includes 22 deaths and 235 discharges," said the State government COVID-19 bulletin.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.