Major blow to Adani's Udupi power project; NGT declares clearances granted to set up plant are illegal

coastaldigest.com news network
March 16, 2019

Udupi, Mar 16: In a major blow to Adani's Udupi Power Plant project at Yellur village of Udupi district, the Principal Bench of the National Green Tribunal declared on 14" March 2019 that all the clearances granted to set up the power plant are illegal. It has also ordered the suspension of the Environmental Clearance dated 1.08.2017 granted to expand the plant by addition of 2x800MW units to raise ultimate capacity to 2800MW. The Tribunal invoked the "Polluter Pays" principle and appointed a committee of experts to ascertain the damages to the crops and the environment in general of the area. It has directed the Company to pay 5 crores as an interim environmental compensation to CPCB who will also be the Nodal agency to study the damages caused. It has also ordered the Company to pay Rs. 1 lakh as cost to the Petitioners.

The Tribunal found that genuinely serious issues raised by the villagers and the Applicants had not been given the due attention it observed by all concerned including the Government. The fact that multitudes of disputes and litigations relating to the project had been instituted bears witness to the fact that all was not well. Environmental clearance dated 20.03.1997 had been granted without following the due process statutorily prescribed and mandatorily required to be followed. Extension of the validity period of the EC had been granted on 16.04.2002 at the request of the project proponent as work could not be commenced within the 5 years' period stipulated in the EC. This is without authority of law. On 05.10.2004 the EC was cancelled by the Ministry as the project proponent had still not commenced with the work of the project. This order of cancellation was recalled vide a personal letter dated 31.01.2005 by the Director MOEF under questionable circumstances at the request of the project proponent.

The Tribunal pointed out that the procedures laid down under the EIA Notifications are not mere formalities to be followed but have been prescribed to ensure that the environment is duly protected while taking up a project keeping in view the Precautionary Principle and the principle of Sustainable Development. The fact that the procedures prescribed in the Notification were not at all followed except few parts of it, lead it to reasonably conclude that there has been damage caused to the environment for which consequences have fallen on the people in terms of healtn, decline in the agricultural productivity and, therefore, their livelihood, degradation of natural habitat of birds and animals, etc.

Tribunal took a serious note of the study carried out on "Environmental Profile and People's Livelihood aspects in the vicinity of Coal Based Thermal Power Plant at Yellur Panchayat, Udupi District" by a group of Scientists as CES Technical Report 126 dated April 2012 published by the Energy & Wetland Research Group, Centre for Ecological Sciences, Indian Institute of Science, Bangalore, has made alarming observations in respect of the project area during field investigations. It has been observed that mismanagement of the environment was evident from the contamination of the water (surface and ground), soil and air apart from the impaired functional aspects of the biotic elements. This was deduced from the reduced productivity of grains, jasmine flower and horticultural produce, reproductive ability of livestock, poultry animals, etc. There was dust on the leaves during the dry seasons which induced phyto-toxicity leading to poor pollination and hence reduced productivity. There was reduction in the population of pollinators. Stunted growth of saplings and enhanced respiratory diseases, etc. were noticed caused by release of saline mist from the cooling towers of the plant which is locally dispersed by the wind even up to 2 kms.

The Tribunal found the conduct of the MoEF&CC in the entire episode does not appear to be above board. The Tribunal expresses grave anguish and concern which in its view ought to be corrected and left it upon the MoEF&CC to deal with this aspect as their wisdom may dictate.

The Tribunal observed that justifiably, therefore, the directions would be called for to remove the plant and order for restoration of the area and the environment. However, considering the facts and circumstances, the lapse of time and the fait accompli situation that has arisen, we are of the view that the interest of public will not be served in passing such order. The need of the hour is to explore such measures and steps that would mitigate the harm already caused in addition to ensuring that the plant operates strictly within the environmental norms. It has thus invoked the "Polluter Pays" principle under Section 20 of the National Green Tribunal Act, 2010 and hold M/s. Udupi Power Corporation Ltd., the Respondent No. 5, project proponent, liable to pay Environmental Compensation which shall bg assessed by a Committee of Experts. It has constituted a Committee comprising of- 1. Senior Scientist, CPCB. 2. Senior Representative, IIT Chennai. 3. Senior Scientist, IIT Bangalore. CPCB shall be the nodal agency to coordinate amongst the Members for taking up the task.

The Committee shall assess the environmental damage on account of the environmental violations and submit its report within three months. Awaiting such report, it directed UPCL to pay an interim Environmental Compensation of k5 crores with the CPCB. The interim compensation would be subject to assessment of final damages by the Committee of Experts. This amount shall be deposited within a period of one month from hence. The CPCB, in the meanwhile, shall utilize the interim compensation for restitution and remedial works for restitution of the environment including the possible plight of the people affected by the plant. It has made it clear that this amount shall be distinct from the other obligations of UPCL under the Corporate Social Responsibility (CSR) or other obligations.

The project was challenged as early as in 2004 by the Samithi before the then National Environmental Appellate Authority (NEAA), New Delhi. The appeal was dismissed by the sole non-judicial adjudicator who was formerly the Secretary, MOEF responsible earlier for the grant of the very Environmental Clearance. Aggrieved by the decision, the Samithi filed WP before the Karnataka High Court in 2005. Bellibettu Alade Devasthana and CSI St. Luke's Church also filed separate Writ Petitions before the High Court. The cases were transferred to the National Green Tribunal South Zone, Chennai in 2012 under the Supreme Court order. Due to the lack of Judges in Zonal Tribunal at Chennai the cases were finally heard by the Principal Bench at New Delhi and the judgement was released on 14th March 2019. The State of Karnataka actually does not need power from the plant and Govt has either stopped or considerably reduced receiving the supply from UPCL. The Energy Dept website show that as on 31.07.2018 the total generation of power from various sources has increased to 27,176.43 MW out of which 4,713.26 MW is Wind Energy and 5,172.72 MW is Solar among others. The website also shows that the available potential of the Renewable Energy totals to 86,792MW of which Wind Energy is 55,857MW and Solar 24,700MW. With such RE potential the killer coal-based power plants are not at all required in the State leave alone in the sensitive Ecologically Coastal Zone.

As such the State Govt is required to issue directions to UPCL to shut it down and shift it to another place perhaps another country like Bangladesh. It has also come to the knowledge of the Samithi that UPCL is now planning new Transmission Lines to supply power to other State perhaps through the grid at Kerala. It would only mean that we would be used as sacrificial lambs for the Company and this will not be acceptable.

Comments

jaleel
 - 
Monday, 18 Mar 2019

Now even the plant is shut, it's the public who are at lose. Govt provided public money to Mota bhai to set up this plant. Coorporate sect always play with public life, money. They keep people busy in fake and unwanted issues and politicians prepare grounds for all these nuisance. Tuticorn in Tamilnadu and likewise many examples are in front of us. This will happen again and again We are fools really. At least for the sake of our next generation we should start thinking like a man not like donkey  

 

 

 

 

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
April 25,2020

Bengaluru, Apr 25: Karnataka Health Minister B Sriramulu on Saturday initiated Phase I clinical trials to use plasma therapy for COVID-19 patients at city-based BMC Victoria Hospital.

Sriramulu was accompanied by Medical Education Minister Dr K Sudhakar.

"Karnataka has taken a lead role as we initiate Phase I clinical trials to use Convalescent Plasma Therapy for severe COVID-19 infected patients. BMC Victoria hospital took the first step today. We are determined to vanquish this enemy of mankind," Sriramulu said in a tweet.

"I wish our team of doctors at BMC Victoria hospital and team led by Dr US Vishal Rao a great success. This will be a torchbearer in our fight against Corona," he said in another tweet.

According to the Ministry of Health and Family Welfare, the state has so far reported 474 confirmed cases of COVID-19 which include 152 discharged or cured patients and 18 deaths.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
June 22,2020

Bengaluru, Jun 22: The Central Crime Branch (CCB) of Bengaluru Police has obtained the custody of an associate of gangster Ravi Pujari and is questioning him about his role in several cases against the gangster, the police said on Monday.

According to the police, Khan is convicted in the case related to the murder of a builder named Subba Rao in the year 2017. The accused has been identified as Yousuf Bacha Khan.

"Continuing the investigation of Ravi Poojary, CCB had obtained custody of Yousuf Bacha Khan, who is associate of Pujari. Khan was convicted in the Subba Rao murder case. He is being questioned about his role in other cases," Joint Commissioner of Police (Crime) Sandeep Patil said.

The CCB had recently filed two charge sheets against gangster Ravi Pujari in Shabnam developers double murder case and an extortion case.

Pujari, who was wanted in several cases including ones related to heinous crimes like murder and extortion, was extradited to Bengaluru earlier this year from Senegal.

The gangster, who parted ways with underworld don Chhota Rajan, had jumped bail after he was arrested in Senegal in 2019 and had escaped to South Africa, where he was involved in drug trafficking and extortion.

According to sources in the Indian intelligence, Ravi Pujari was hiding under the false identity of Anthony Fernandes, a Burkina Faso passport holder, in a remote village in South Africa.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
August 5,2020

Shivamogga, Aug 5: Karnataka Minister KS Eshwarappa on Wednesday hailed the laying of foundation stone (bhoomi pujan) for a grand Ram temple in Ayodhya and said "Kashi Vishwanath and "Krishna Janmasthan temples have to be liberated".

"It is a good day that the foundation stone for Ram Temple has been laid. A beautiful temple will come up, but there are Kashi Vishwanath and Krishna Janmasthan temples which have to be liberated," Eshwarappa said.

The minister said that there is a "sign of slavery" at Krishna temple in Mathura and Kashi Vishwanath temple in Varanasi.

"The whole nation is dreaming of Shri Krishna temple in Mathura and Kashi Vishwanath temple. I have visited the two temples. 

There is a sign of slavery. Mosques are there at holy places. When I visited the place at Mathura, I witnessed the wall. When we look at the wall, we feel like we are still slaves," he said.

"While visiting Kashi, there is also a structure of slavery. Dream of Hindus is fulfilled in Ayodhya. One day, it will be fulfilled in Mathura and Kashi. Mathura Sri Krishna and Kashi Vishwanath will be freed and temple will be built," Eshwarappa added.

The Places of Worship Act, enacted in 1991, says that religious character of a place of worship existing on the August 15, 1947 shall continue to be the same as it existed on that day. The Act kept Ayodhya case out of its purview.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.