Mangaluru International Airport's taxiway to be extended to 2,400 metres

[email protected] (CD Network)
July 16, 2016

Mangaluru, Jul 16: Mangaluru International Airport will soon have a long additional taxiway as the Board of the Airports Authority of India (AAI) has recently approved the extension of the taxiway being built now to length of 2,400 metres long.

1taxiTaxiway is the stretch or the track connecting the runway with the apron (parking stand for aircrafts) in the terminal building. Aircraft use the taxiway for entry and exit from the parking stand to the runway.

The additional taxiway being built at the airport since August 2014 is 1,200 metres long and 23 metres wide. Its work is expected to be completed by next two months. The AAI board has now agreed and approved to extend the taxiway further by another 1,200 metres to make it a 2,400 metres long taxiway.

The current first phase work under progress is being implemented at a cost of Rs. 40 crore and second phase will cost Rs 106 crore as a deep valley has to be filled.

The additional taxiway particularly helps aircraft in saving time in the entry and exit from the parking stand to the runway. Airport Director J T Radhakrishna said that as of now, aircraft that are ready to take off have to wait for 10 to 15 minutes if their departure timing clashes with a flight that is scheduled to land, due to the procedures involved. It has to wait till the arriving plane completes its course on the runway and rolls into the apron.

With the additional taxiway in place, aircraft could move from the parking stand, wait in the additional taxiway and enter the runway for take off immediately after the plane that has landed exits the runway. Once the additional taxiway is ready, there would be separate and fixed entry and exit paths.

The additional taxiway particularly helps in the long run when the number of flights increases in the airport.

Mr. Radhakrishna said that bids for taking up the II Phase work is likely to be called in October. The works might start from January or February next. The contractor would have a year to complete the work, he added.

Comments

Rajesh Sequira
 - 
Sunday, 17 Jul 2016

This is good news to hear that there is continuous development at Mangalore Airport.

Admadi
 - 
Sunday, 17 Jul 2016

Boss we dont need taxi/bus/train ways, we need only safest runways to land international flights. saale sab chor hi

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
July 17,2020

Bengaluru, Jul 17: Karnataka Medical Education Minister K Sudhakar held a meeting through video conference on Thursday with private and government establishments involved in testing and treatment of COVID-19 in the state.

A total of 51,422 cases including 19,729 recoveries and 1,032 deaths were reported in the state till yesterday.

On the same day, K Sudhakar also paid a surprise visit to the Bengaluru's CV Raman Hospital and urged the administration to follow COVID-19 guidelines properly. He also took stock of the hospital's preparedness to fight the deadly virus.

"Surprise visits will continue. I will be in touch with every lab and get the right number of tests done on a daily basis," the minister said while speaking to the media.

He also urged the people who have recovered from coronavirus to donate their plasma to save other lives, adding that donors will receive a reward of Rs 5,000 as a token of appreciation.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
January 7,2020

Udupi, Jan 7: Eshapriya Teertha Swamiji, who was appointed as the junior Swamiji of Admar Math, would be ascending the 'Paryaya Peeta' for the first time on January 18, Vishwapriya Theertha Swamiji of Admar Math said.

Speaking to the media at Admar Moola Math at Admar near Padubidri on Monday night Vishwapriya Teertha Swamiji of Admar Math said, 'I had performed my first Paryaya in 1988-90 with the help of Shri Vishwapriya Teertharu.

'The second Paryaya was performed independently by the order of Shri Vibudhesha Teertharu in 2004-06.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
July 19,2020

Bengaluru, Jul 19: The Karnataka Deputy Chief Minister C N Ashwathnarayan on Saturday inspected the country's first modular Intensive Care Unit (ICU) containers.

A notice from the Chief Minister's Office (CMO) said that the new mobile modular container ICUs, which will be used in the fight against the ongoing COVID-19 pandemic, have been created by Rinac India Limited, known for setting up sanitised operation theatres and clean rooms in hospitals.

On a pilot basis, the Deputy CM, who is also in charge of setting up COVID-care centres, said that 10 modular container ICUs will be deployed at the KC General Hospital in Malleshwaram. Each of the containers will have five beds.

Deputy CM Ashwathnarayan also said, "These mobile ICUs donated by Rinac will be useful, particularly in times of a crisis like COVID 19 or any natural calamity."

"The entry of health officials will be through an airlock, and entry of patients will be through a different door. There will be two doors for patients and can be increased if need. ICUs are fitted with cameras to monitor online from a centralized monitoring station, thereby limiting the exposure of the health personnel," the CMO informed.

The CMO further added, "the advantages of this new system are that the prefabricated modules of 5 can be shifted to any location by trailers and it is easy to deploy multiple containers to create a common facility. They are easy to clean and the airtight functionality ensures that no moisture or heat ingression happens, hence, it is easy to air-condition or ventilate."

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.