CAG reports slam UPA government, BJP demands PM's resignation

August 17, 2012

coal

New Delhi, August 17: Three key CAG reports were tabled in Parliament on Friday indicting the government of causing a combined loss of crores of rupees to the national exchequer.

The much-awaited CAG report on coal block allotment said private firms are likely to gain Rs 1.86 lakh crore from coal blocks that were allocated to them on nomination basis instead of competitive bidding.

The audit report on Delhi airport slams the levy of development fee on passengers and says the civil aviation ministry violated the bid conditions for the benefit of GMR-led DIAL to the tune of over Rs 3,415 crore.

The third CAG report flays post-bid concessions to Reliance Power and says the Anil Ambani-led firm got undue benefit of Rs 29,033 crore when the government allowed use of surplus coal from blocks alloted to Sasan power plant for its other projects.

Reacting to the CAG reports, minister of state in Prime Minister's office V Narayanasamy said that the govt auditor was not following its mandate.

Meanwhile, the BJP demanded resignation of the government alleging that scams in the coal, power and airport sectors had exposed the "loot and plunder" of the country. "

The party sought Prime Minister's resignation as he headed the coal ministry at the time of alleged irregularities.

Government is badly exposed by the three CAG reports on power, coal and Delhi airport. The magnitude of these scams, according to the CAG report, is between Rs 1.6 and 1.86 lakh crore," BJP spokesperson Prakash Javadekar told reporters outside Parliament.

CAG's coal report

The CAG in its report, tabled in Parliament, names 25 companies including Essar Power, Hindalco, Tata Steel, Tata Power and Jindal Steel and Power which have got the blocks in various states.

"Delay in introduction of the process of competitive bidding has rendered the existing process beneficial to the private companies. Audit has estimated financial gains to the tune of Rs 1.86 lakh crore likely to accrue to private coal block allottees," CAG said in a report on allocation of coal blocks. The CAG said it has arrived at the estimates based on the average cost of production and average sale price of opencast mines of Coal India in the year 2010-11.

"A part of this financial gain could have accrued to the national exchequer by operationalising the decision taken years earlier to introduce competitive bidding for allocation of coal blocks," CAG said.

The auditing body said it is "of strong opinion that there is a need for strict regulatory and monitoring mechanism to ensure that benefit of cheaper coal is passed on consumers".

The concept of allocation of captive coal blocks through competitive bidding was announced in 2004. However, government is yet to finalise the modus operandi of competitive bidding.

CIL suffered 116 MT output loss due to delays in projects: CAG

The world's largest miner Coal India (CIL) suffered production losses to the tune of 116 million tonnes (MT) on account of delays in execution of new projects, government auditor CAG has said.

Delays ranging from "one to 12 years" in execution of 32 projects under different subsidiaries of CIL entailed "loss of production by 115.95 MT," CAG said in its report on "Allocation of Coal Blocks and Augmentation of Coal Production".

The delays, it said, pertained to "problems of land acquisition, forest clearance, adverse geo-mining condition, tender finalisation for equipment of and construction of Coal Handling Plant (CHP) and railway siding," it said.

CAG observed that delays took place despite an expert committee emphasising way back in 2005 the need for setting up of a permanent special task force to monitor progress of clearances and project implementation of schemes to be completed by the end of XIth Five Year Plan (2007-12).

"In order to bridge the demand-supply gap of coal, new coal projects are required to be completed in a time bound manner," it said.

However, the coal ministry stated in January, 2012 that "response from ministry of environment and forest is awaited."

Noting that CIL could not match with the rate of increase in coal production due to delays in execution of augmentation of projects on account of "lack of coordinated and planned approach by various government agencies involved in statutory clearances and land execution," CAG asked CIL to fix output targets in line with the targets by the Planning Commission.

State-run Coal India is the largest domestic producer of dry-fuel and accounts for over 80 per cent of the total domestic production.

CAG's report on Delhi airport

CAG in its audit report on Indira Gandhi International Airport that was tabled in Parliament, said DIAL can potentially earn Rs 1,63,557 crore over a 60-year period from the land given to it on a lease of Rs 100 per annum.

Allowing DIAL to levy development fee vitiated the sanctity of bidding process and led to undue benefit of Rs 3,415.35 crore to the private firm, it said.

GMR Infrastructure holds 54 per cent stake in Delhi International Airport Ltd (DIAL).

"It was noticed that ministry of civil aviation and Airport Authority of India, on some occasions, violated the provisions of the transaction documents in the interest of the concessionaire," the official auditor said.

CAG said contrary to provision of the airport concession agreement, DIAL was allowed to use the amount collected as development fees to meet the project costs.

"In face, only 19 per cent of the project cost came from equity, approximately 42 per cent came from debt. The remaining project costs were met from security deposits and development fees".

"Whenever DIAL raised an issue regarding revenue to accrue to it or expenditure to be debited to government in contravention to the provisions of Operation Management Development Agreement (OMDA), the ministry and AAI interpreted the provisions always in favour of the operators and against the interest of the government," it said.

CAG report on Reliance Power

Flaying post-bid concessions to Reliance Power, the CAG has said the Anil Ambani-led firm got undue benefit of Rs 29,033 crore when the government allowed use of surplus coal from blocks alloted to Sasan power plant for its other projects.

CAG in its report tabled in Parliament said subsequent to award of the 4,000 MW Sasan ultra mega power project to RPL, the government granted permission to the company to utilise the surplus coal from three mines attached to the projects for the group's Chitrangi project in Madhya Pradesh.

"A reading of all the clauses in the allocation letters together conveyed that clauses were inserted in the coal allocation letter as a safegaurd measure to prevent misuse of coal by the developer. The permission to use surplus coal in other projects of the bidder after award of the contract based on acceptance of the lowest tariff, vitiated the sanctity of the bidding process which would result in post bid concessions to the developer having significant financial implication," it said.

CAG said the permission to use of excess coal from Moher, Moher Amlohri and Chhatrasal blocks allocated to RPL's Sasan power project after its award "not only vitiated the bidding process but also resulted in undue benefit to RPL".

"This decision resulted in financial benefit of Rs 29,033 crore with a net present value of Rs 11,852 crore to the project developer (RPL)," the official auditor said.

CAG said it was not clear how power ministry in October 2006 came to the conclusion that two initially allocated blocks for the Sasan project (Moher and Moher Amlohri) would be inadequate to fire the 4,000 MW plant.

"The basis on which ministry of coal was prevailed upon in October 2006 itself to allot an additional block (Chhatrasal) of coal to Sasan ultra mega power project by de-allocating it from the public sector NTPC is not clear," it said.


Normal 0 false false false EN-US X-NONE X-NONE

CAG reports slam UPA government, BJP demands PM's resignation

New Delhi, August 17: Three key CAG reports were tabled in Parliament on Friday indicting the government of causing a combined loss of crores of rupees to the national exchequer.

The much-awaited CAG report on coal block allotment said private firms are likely to gain Rs 1.86 lakh crore from coal blocks that were allocated to them on nomination basis instead of competitive bidding.

The audit report on Delhi airport slams the levy of development fee on passengers and says the civil aviation ministry violated the bid conditions for the benefit of GMR-led DIAL to the tune of over Rs 3,415 crore.

The third CAG report flays post-bid concessions to Reliance Power and says the Anil Ambani-led firm got undue benefit of Rs 29,033 crore when the government allowed use of surplus coal from blocks alloted to Sasan power plant for its other projects.

Reacting to the CAG reports, minister of state in Prime Minister's office V Narayanasamy said that the govt auditor was not following its mandate.

Meanwhile, the BJP demanded resignation of the government alleging that scams in the coal, power and airport sectors had exposed the "loot and plunder" of the country. "

The party sought Prime Minister's resignation as he headed the coal ministry at the time of alleged irregularities.

Government is badly exposed by the three CAG reports on power, coal and Delhi airport. The magnitude of these scams, according to the CAG report, is between Rs 1.6 and 1.86 lakh crore," BJP spokesperson Prakash Javadekar told reporters outside Parliament.

CAG's coal report

The CAG in its report, tabled in Parliament, names 25 companies including Essar Power, Hindalco, Tata Steel, Tata Power and Jindal Steel and Power which have got the blocks in various states.

"Delay in introduction of the process of competitive bidding has rendered the existing process beneficial to the private companies. Audit has estimated financial gains to the tune of Rs 1.86 lakh crore likely to accrue to private coal block allottees," CAG said in a report on allocation of coal blocks. The CAG said it has arrived at the estimates based on the average cost of production and average sale price of opencast mines of Coal India in the year 2010-11.

"A part of this financial gain could have accrued to the national exchequer by operationalising the decision taken years earlier to introduce competitive bidding for allocation of coal blocks," CAG said.

The auditing body said it is "of strong opinion that there is a need for strict regulatory and monitoring mechanism to ensure that benefit of cheaper coal is passed on consumers".

The concept of allocation of captive coal blocks through competitive bidding was announced in 2004. However, government is yet to finalise the modus operandi of competitive bidding.

CIL suffered 116 MT output loss due to delays in projects: CAG

The world's largest miner Coal India (CIL) suffered production losses to the tune of 116 million tonnes (MT) on account of delays in execution of new projects, government auditor CAG has said.

Delays ranging from "one to 12 years" in execution of 32 projects under different subsidiaries of CIL entailed "loss of production by 115.95 MT," CAG said in its report on "Allocation of Coal Blocks and Augmentation of Coal Production".

The delays, it said, pertained to "problems of land acquisition, forest clearance, adverse geo-mining condition, tender finalisation for equipment of and construction of Coal Handling Plant (CHP) and railway siding," it said.

CAG observed that delays took place despite an expert committee emphasising way back in 2005 the need for setting up of a permanent special task force to monitor progress of clearances and project implementation of schemes to be completed by the end of XIth Five Year Plan (2007-12).

"In order to bridge the demand-supply gap of coal, new coal projects are required to be completed in a time bound manner," it said.

However, the coal ministry stated in January, 2012 that "response from ministry of environment and forest is awaited."

Noting that CIL could not match with the rate of increase in coal production due to delays in execution of augmentation of projects on account of "lack of coordinated and planned approach by various government agencies involved in statutory clearances and land execution," CAG asked CIL to fix output targets in line with the targets by the Planning Commission.

State-run Coal India is the largest domestic producer of dry-fuel and accounts for over 80 per cent of the total domestic production.

CAG's report on Delhi airport

CAG in its audit report on Indira Gandhi International Airport that was tabled in Parliament, said DIAL can potentially earn Rs 1,63,557 crore over a 60-year period from the land given to it on a lease of Rs 100 per annum.

Allowing DIAL to levy development fee vitiated the sanctity of bidding process and led to undue benefit of Rs 3,415.35 crore to the private firm, it said.

GMR Infrastructure holds 54 per cent stake in Delhi International Airport Ltd (DIAL).

"It was noticed that ministry of civil aviation and Airport Authority of India, on some occasions, violated the provisions of the transaction documents in the interest of the concessionaire," the official auditor said.

CAG said contrary to provision of the airport concession agreement, DIAL was allowed to use the amount collected as development fees to meet the project costs.

"In face, only 19 per cent of the project cost came from equity, approximately 42 per cent came from debt. The remaining project costs were met from security deposits and development fees".

"Whenever DIAL raised an issue regarding revenue to accrue to it or expenditure to be debited to government in contravention to the provisions of Operation Management Development Agreement (OMDA), the ministry and AAI interpreted the provisions always in favour of the operators and against the interest of the government," it said.

CAG report on Reliance Power

Flaying post-bid concessions to Reliance Power, the CAG has said the Anil Ambani-led firm got undue benefit of Rs 29,033 crore when the government allowed use of surplus coal from blocks alloted to Sasan power plant for its other projects.

CAG in its report tabled in Parliament said subsequent to award of the 4,000 MW Sasan ultra mega power project to RPL, the government granted permission to the company to utilise the surplus coal from three mines attached to the projects for the group's Chitrangi project in Madhya Pradesh.

"A reading of all the clauses in the allocation letters together conveyed that clauses were inserted in the coal allocation letter as a safegaurd measure to prevent misuse of coal by the developer. The permission to use surplus coal in other projects of the bidder after award of the contract based on acceptance of the lowest tariff, vitiated the sanctity of the bidding process which would result in post bid concessions to the developer having significant financial implication," it said.

CAG said the permission to use of excess coal from Moher, Moher Amlohri and Chhatrasal blocks allocated to RPL's Sasan power project after its award "not only vitiated the bidding process but also resulted in undue benefit to RPL".

"This decision resulted in financial benefit of Rs 29,033 crore with a net present value of Rs 11,852 crore to the project developer (RPL)," the official auditor said.

CAG said it was not clear how power ministry in October 2006 came to the conclusion that two initially allocated blocks for the Sasan project (Moher and Moher Amlohri) would be inadequate to fire the 4,000 MW plant.

"The basis on which ministry of coal was prevailed upon in October 2006 itself to allot an additional block (Chhatrasal) of coal to Sasan ultra mega power project by de-allocating it from the public sector NTPC is not clear," it said.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
July 14,2020

Kathmandu, Jul 14: After staking claim to Indian territories of Lipulekh-Kalapani in  a new controversial map,  Nepal Prime Minister KP Sharma Oli on Monday claimed that Ayodhya, the birthplace of Lord Rama, is in Nepal and Lord Rama was Nepali.

“Although real Ayodhya lies at Thori, city in the west of Birgunj, India has claimed that Lord Rama was born there. Due to these continuous claims, even we have believed that deity Sita got married to Prince Rama of India. However, in reality, Ayodhya is a village lying west of Birgunj,” Oli claimed at an event organised at Prime Minister's residence in Kathmandu.

The Prime Minister also blamed India of cultural encroachment by “creating a fake Ayodhya.”

“Balmiki Ashram is in Nepal and the holy place where King Dashrath had executed the rites to get the son is in Ridi. Dashrath’s son Ram was not an Indian and Ayodhya is also in Nepal,” he claimed.

In an attempt to save self from criticism, Oli questioned how Lord Rama could come to Janakpur to marry Sita when there were "no means" of communication. He further said that it to be impossible for Lord Rama to come to Janakpur from present Ayodhya that lies in India.

“Janakpur lies here and Ayodhya there and there is talk of marriage. There was neither telephone nor mobile then how could he know about Janakpur,” Oli said.

Comments

Ahmed Ali Kulai
 - 
Tuesday, 14 Jul 2020

New controversy

 
BJP got next election Muddah

Farhan
 - 
Tuesday, 14 Jul 2020

Ab Ram Mandir Kaha Banega???

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
coastaldigest.com web desk
August 1,2020

New Delhi, July 1: In a terrific incident with chilling echoes of the 2015 Dadri mob lynching, a Muslim man, who was carrying meat, was savagely attacked by a mob belonging to a saffron outfit in the presence of in BJP ruled Haryana on the eve of Eid al-Adha. 

The incident occurred at around 9 a.m. on Friday, July 31 at Badshahpur village in Haryana’s Gurgaon, when Lukman was transporting meat in a pic-kup truck. 

The attack was captured on mobile phones by onlookers and the video clips of the incident are now spreading on social media. 

A group of saffronite cow vigilantes chased the truck for about 8 km managed waylay it. Lukman, who was driving the truck was pulled out and brutally assaulted on the suspicion that he was transporting cow meat.

Just like Dadri, the police were faster at sending the meat to a lab for testing than catching any one of the suspects. One of the assailants - Pradeep Yadav- has been arrested. 

After being beating to an inch of his life, Lukman was bundled into the pick-up truck and taken back to Gurgaon's Badshahpur village where the goons started thrashing him again.

This is when the police stepped in and stopped them - only to find the assailants fearless enough to even take on them.

Lukman was taken to a hospital and the police filed a case against "unidentified individuals" even though the video of the incident recorded by witnesses shows the faces of the assailants.

The owner of the vehicles said that the meat was buffalo and he has been in the business for 50 years.

The police have so far refused to give a statement on record on the incident and explain their inaction as seen on video.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
April 12,2020

New Delhi, Apr 12: With 34 deaths and 909 new positive COVID-19 cases in the last 24 hours, the total number of coronavirus cases in India on Sunday climbed to 8356, including 716 cured and discharged and 273 deaths, said the Ministry of Health and Family Welfare.

At present, there are 7367 active COVID-19 cases in the country.

"A total number of COVID-19 positive cases rises to 8356 in India, including 716 cured/discharged, 273 deaths and 1 migrated," said the Health Department.

The highest number of positive cases of coronavirus was reported from Maharashtra at 1761, including 127 deaths, followed by Delhi (1069 and 19 deaths), Tamil Nadu (969 and 10 deaths) and Rajasthan (700 and 3 deaths).

There are 452 coronavirus positive cases in Uttar Pradesh, including 45 cured and discharged and 5 deaths.

The states which have crossed 200-mark for COVID-19 positive cases also include Madhya Pradesh (532), Telangana (504), Gujarat (432), Andhra Pradesh (381) and Kerala (364).

While 19 people were detected positive for coronavirus in Chandigarh, 207 cases were confirmed from Jammu and Kashmir and 15 from Ladakh.

In North-East, Assam has confirmed the highest number of corona positive cases at 29, followed by Manipur and Tripur at two each and Mizoram, Arunachal Pradesh at one each.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.