Modi’s jobs deficit: J&J’s largest India plant idle 3 years after completion

Agencies
May 19, 2019

New Delhi, May 19: It was supposed to be Johnson & Johnson’s biggest manufacturing plant in India. It was to eventually employ at least 1,500 people and help bring development to a rural area near Hyderabad in southern India.

Yet, three years after the US healthcare company completed construction of production facilities for cosmetics and baby products on the 47-acre site, they stand idle.

Two sources familiar with J&J’s operations in India and one state government official told Reuters production at the plant, at Penjerla in Telangana, never began because of a slowing in the growth in demand for the products.

One of them said that demand didn’t rise as expected because of two shock policy moves by Prime Minister Narendra Modi: a late 2016 ban on then circulating high-value currency notes, and the nationwide introduction of a goods and services tax (GST) in 2017.

J&J spokespeople in its Mumbai operations in India and at its global headquarters in New Brunswick, New Jersey, declined to respond to a list of questions from Reuters.

Modi’s office did not respond to a call and an email with questions.

Aimed at rooting out corruption and streamlining the tax system, the double whammy of ‘demonetization’ and GST – were two of Modi’s signature policy moves. But instead of encouraging economic activity as intended, they did the opposite, at least in 2016-2018, by sapping consumer demand, according to some economists.

Many businesses, especially small and medium-sized enterprises, complained publicly – some in their financial statements - that they suffered a drop off in orders. The suspended J&J project stands as one of the most vivid examples of the impact on the broader investment picture.

In the first month after demonetisation, some business surveys showed that sales of products such as shampoos and soap fell more than 20 per cent.

Lack of jobs growth and a farm-income crisis because of low crop prices have hurt Modi in the current general election, according to several political strategists.

Still, Modi and his ruling Hindu nationalist Bharatiya Janata Party are expected by many of the strategists to be in a position to get a second term – probably with support of some other parties - when votes are counted on Thursday, partly because of his strong stance on national security issues.

BIG INVESTMENTS, GREAT EXPECTATIONS

A range of Modi’s business policies, such as capping prices of medical devices, forcing tech companies to store more data locally and stricter e-commerce regulations have in the past two years hurt plans of American multinationals such as J&J, Mastercard, Amazon and Walmart-owned Flipkart.

The groundbreaking of the J&J facility in Penjerla, its third in the country, was carried out with much fanfare in 2014, attended by Telangana’s Chief Minister Chandrashekar Rao, who hailed the foreign investment as a big win for local communities.

A document dated April 2017 that lists products the company planned to make at the facility, submitted to the Telangana government and reviewed by Reuters, names baby oil, baby shampoo, baby lotion, baby hair oil, face wash and creams.

Shaukat Ali, running a tea shop under a bamboo stall on barren land outside the plant, said local workers check in routinely for possible vacancies at the J&J site, but nothing has come up in years.

At the local pollution control board office, the member secretary Satyanarayana Reddy said the J&J plant had all the required approvals and he was not sure why it hadn’t started production.

“It is unusual for such a big plant to stay idle for so long,” he said. “But there is no problem from our side.”

Chandrasekhar Babu, an additional director at the Telangana industries department, said a J&J company official told him the plant hadn’t started due to lack of demand.

GST and demonetisation were two key reasons the plan didn’t kick off, one of the sources said, adding that lack of consumer demand since then dented company’s plans.

The second source familiar with J&J’s plans said the company miscalculated Indian market demand.

On a recent visit by a Reuters reporter to the J&J plant, plush, furnished conference rooms and cubicles sat inactive; M. Sairam, who said he was the site manager, told Reuters production areas with machines were idle too.

PLANNED FURTHER EXPANSION

Local officials had hoped the initial J&J plant would be only the beginning. After the groundbreaking in 2014, Pradeep Chandra, who was Telangana’s special chief secretary of industries, told Business Today magazine that “based on the extent of land (J&J) have acquired we believe that they are looking at much larger expansion here.”

Local media reports at the time said the J&J facility would employ some 1,500 people.

A J&J official, who was not identified by name, was reported subsequently in December 2016 in India’s Business Standard as saying that the $85 million plant would be operational by 2018 after it had overcome procedural delays. The official was quoted as saying the company had earmarked an additional $100 million for expansion.

Vikas Srivastava, the managing director of J&J Consumer(India), who was at the 2014 groundbreaking, did not respond to calls for comment.

Reuters also talked to two workers outside a sprawling Procter & Gamble facility making detergents and diapers, which is next to the J&J plant. They said they were part of the P&G plant’s production team and the plant had been running below capacity.

A P&G spokesperson denied that, saying the plant was “operating at full capacity in line with our business plans”.

“India is a priority market for P&G globally and in recent quarters, P&G’s business in India has registered strong double-digit growth consistently,” the company said.

The weak rural economy, where most Indians work, has also hurt growth in sales of basic items such as detergents and shampoo in the past year.

Hindustan Unilever Ltd, an industry bellwether that would compete with the likes of J&J and P&G in some categories, said its volume growth shrank to 7 percent in the quarter ended March 31, down from double-digit growth in the previous five quarters.

The company warned that the daily consumer goods segment in India was “recession resistant ... not recession proof.”

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
January 31,2020

New Delhi, Jan 31: Nirbhaya's mother Asha Devi on Friday said she will continue her fight till the convicts in the 2012 gangrape and murder case are hanged, shortly after a Delhi court postponed the execution of death warrants till further order.

Devi told reporters her "hopes are dashed" but she will continue her fight.

"These convicts have no right to live. We keep getting disappointed by the system. I will continue my fight till the convicts are hanged," she said.

A Delhi court postponed the execution of death warrants of the four convicts in the Nirbhaya gangrape and murder case till further order.

Additional sessions judge Dharmender Rana passed the order on a plea by the convicts seeking a stay on their execution on Saturday, February 1.

Devi said because of the loopholes in law the "criminals' lawyers had the audacity to challenge me in court that they will not be hanged".

The black warrants for execution of the death sentence against Pawan Gupta, Vinay Kumar Sharma, Akshay Kumar and Mukesh Kumar Singh, were issued on January 17.

A 23-year-old physiotherapy intern who came to be known as "Nirbhaya" (the fearless one) was gangraped and savagely assaulted on the night of December 16, 2012, in a moving bus in South Delhi. She died of her injuries a fortnight later in a Singapore hospital.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
February 22,2020

Washington, Feb 22: US President Donald Trump will raise the issue of religious freedom with Prime Minister Narendra Modi during his visit to India next week, the White House said on Friday, noting that the US has great respect for India's democratic traditions and institutions.

"President Trump will talk about our shared tradition of democracy and religious freedom both in his public remarks and then certainly in private. He will raise these issues, particularly the religious freedom issue, which is extremely important to this administration," a senior official told reporters in a conference call.

The official was responding to a question on whether the president was planning to speak to Modi on the Citizenship (Amendment) Act or the National Register of Citizens.

"We do have this shared commitment to upholding our universal values, the rule of law. We have great respect for India's democratic traditions and institutions, and we will continue to encourage India to uphold those traditions," the official said, requesting anonymity.

"And we are concerned with some of the issues that you have raised," the senior administration official said, in response to the question on CAA and NRC.

"I think the President will talk about these issues in his meetings with Prime Minister Modi and note that the world is looking to India to continue to uphold its democratic traditions, respect for religious minorities," the official said.

"Of course, it's in the Indian constitution -- religious freedom, respect for religious minorities, and equal treatment of all religions. So this is something that is important to the president and I'm sure it will come up," said the official.

Pointing out that India has a strong democratic foundation, the official said India is a country rich in religious, linguistic, and cultural diversity.

"In fact, it's the birthplace of four major world religions," the official noted.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
Agencies
January 16,2020

New Delhi, Jan 16: In trouble brewing for the Gautam Adani-led M/S Adani Enterprises, the Central Bureau of Investigation (CBI) on Thursday said that it has registered a case against former officials of the National Co-operative Consumer Federation (NCCF) and others over alleged irregularities in supply of coal to the Andhra Pradesh Power Generation Corporation (APGENCO) in 2010.

The CBI in its FIR has named Virendra Singh, the then Chairman of the NCCF, G P Gupta, the then MD of the NCCF, S C Singhal, the then Senior Advisor of NCCF, Adani Enterprises Ltd and other unknown public servants and others for criminal conspiracy, cheating and criminal misconduct by public servants.

According to CBI, the case was filed on Wednesday after the preliminary enquiry revealed the crime by the officials named in the FIR and the Adani Enterprises was found to be true.

The FIR alleged that on June 26, 2010, APGENCO floated a tender enquiry for supply of six lakh metric tonnes of imported coal "on free on rail destination" basis to Dr Narla Tata Rao Thermal Station (NTTPS), Vijaywada and Rayalasaleema Thermal Power Plant (RTTP), Kadapa, Andhra Pradesh/RTPP via Kakinada-Vizag-Chennai-Krishnapatnam or any other ports

The same was forwarded by the Chief Engineer, APGENCO to seven PSUs -- PEC Limited, STC Limited, MSTC Limited, NCCF, MMTC, Coal India Limited and SCCL Limited.

The FIR alleged that during the probe, the Adani Enterprises used a proxy company to get the supply contract. It said, "NCCF received bids from six companies -- Adani Enterprises Ltd, Maheshwari Brothers Coal Limited (MBCL), Vyom Trade Links Pvt. Ltd, Swarana Projects Pvt. Ltd, Gupta Coal India Ltd and Kyori Oremen Ltd.

During investigation it was found that Gupta Coal India Ltd had quoted the NCCF margin of 11.3 percent, while the MBCL quoted the margin of 2.25 percent and rest did not quote any margin to the NCCF.

The FIR said the quotes of the Gupta Coal India Ltd, Kyori Oremen Ltd and Swarana Projects Pvt. Ltd were rejected by the NCCF as they were not found to be fulfilling the tender conditions.

"Post tender negotiation was done by senior officials of NCCF to give undue favour to Adani Enterprises Ltd despite it not qualifing the tender (terms)," the FIR said, adding instead of cancelling the bid of Adani Enterprise Ltd, senior management of NCCF conveyed the offer margin to the company through one of its representative -- Munish Sehgal, who was sitting in the NCCF head office. It is prima facie evident that when the bids were being processed at NCCF head office in Delhi, a representative of Adani Enterprises Ltd. was informed regarding their imminent rejection due to non-submission of NCCF margin and also that MBCL was eligible bidder quoted 2.25 percent margin," it alleged.

The CBI in its FIR, further alleged that Adani Enterprises Ltd. had given an unsecured loan of Rs 16.81 crore to Vyom Trade Links Ltd in 2008-09. "And further it was revealed that the bank guarantees of the Adani Enterprises Ltd. and Vyom Trade Links Ltd. were issues by the same branch of the State Bank of India and at the same time," it said.

"It was clear that Adani Enterprises Ltd. presented Vyom Trade Links Ltd. as a proxy company in this particular tender and Vyom Trade Links Ltd. later withdrew its offer on flimsy ground," the CBI FIR said.

"The aforesaid acts of commissions and omissions on the part of the senior management of the NCCF disclose that during their tenure, they acted in a manner unbecoming of public servants and committed irregularities by way of manipulation in the selection of bidders, thereby giving undue favours to Adani Enterprises Ltd. in award of work for supply of coal to APGENCO despite its disqualification," it added.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.