Lokayukta unearths scam in Rs 136-cr infrastructure project

June 2, 2017

Bengaluru, Jun 2: A Lokayukta enquiry report has confirmed large-scale irregularities in handling of Rs 136-crore Bidar infrastructure project fund.i-lok

The report submitted by Lokayukta chief engineer stated that almost all the infrastructure works were executed in violation of the Karnataka Transparency in Public Procurement Act and also by paying more than what the bidder had quoted for the work.

The complaint filed to the Lokayukta in 2014 had stated that certain officials at the district administration in Bidar had siphoned off most of the funds that the Union government and the state governments had released in October 2008.

The chief engineer was directed to make spot visits to inspect the files pertaining to the works taken up by the district administration. Senior IAS officer Harsh Gupta was the deputy commissioner when Rs 136 crore was released to the district for taking up various works.

The fund was released to upgrade Bidar infrastructure in view of “Guru-ta-Gaddi,” a celebration to observe the centenary of Guru Granth Sahib. “Since thousands of devotees were expected at Nanded in Maharashtra, the crowd was also expected to visit the Gurudwara complex and other places in Bidar. Hence, the Centre had allocated Rs 136 crore fund to upgrade the infrastructure in Bidar. This fund was part of the Centre's additional central assistance,” the report said.

The team, led by chief engineer Lokayukta, which inspected the documents in April 2015 found that funds were released in two instalments – one Rs 40.82 crore and another Rs 95.20 crore during September-October 2008. The report stated that the then DC, Bidar, (Harsh Gupta) had requested the state government to exempt these works from the provisions of the Karnataka Transparency in Public Procurement Act. Though the state government had not accorded any exemption, all works were split into piece works of below Rs 5 lakh budget.

'Act violated'

“The works were split only to avoid the provisions of the Karnataka Transparency in Public Procurement Act. The files perused reveal that only short-term tenders were invited. Though there was poor response to the tenders called, the district administration made no attempts to recall the tender. In certain cases, single bidder was allotted the work after negotiations.

All these are in violation of the provisions of Karnataka Transparency in Public Procurement Act. Some works were allotted to the contractors by paying more than the bidding amount,” the report stated.

Even as the district administration took up works worth Rs 114.89 crore by 2011, the state government issued an order in January 2011 directing the administration not to take up any more work.

Lokayukta Justice P Vishwanath Shetty said that he is yet to go through the file. “I was told about this case. However, the file has not been placed before me yet. Besides, I have instructed the officials not to place any file before me out of turn, unless it concerns larger public interest and pertains to serious problems to the general public,” Justice Shetty said.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
May 30,2020

Madikeri, May 30: Environmentalists have opposed the Karnataka Forest Department and the Public Works Department’s move to erect concrete pillars and marking of trees to construct a proposed road from Patti to Todikana within the Talacauvery Wildlife Sanctuary near Talacauvery in Kodagu District.

They have urged for immediate stopping of road works in a protected area.

In a letter to Conservator of Forests, Mysuru Circle, T Heeralal and DCF (Territorial and In-charge Wildlife) S Prabhakaran, the Trustees of Wildlife First K M Chinnappa and A A Poovaiah have termed the road works illegal and violates Supreme Court order on National Parks and Wildlife Sanctuaries.

The letter’s copy has also been sent to Principal Chief Conservator of Forests (Head of Forest Force), and Kodagu Deputy Commissioner urging them to halt the progress of the road works. “Patti and Todikana are at the core of the Talacauvery Wildlife Sanctuary and such unilateral activities without complete approval on completion of the statutorily mandated procedure (both under Forest Conservation Act and Wild Life Protection Act),” the letter stated.

The letter added that they would be forced to move the Courts and the officers who have given approval to the project would face legal consequences.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
March 2,2020

Udupi, Mar 2: The Kundapur police carried out raids at various clubs in Kundapur Sub-division limits and arrested around 50 persons involved in illegal gambling and seized Rs 2.5 lakhs from their possession, the police said on Monday.

According to the police, on Sunday night, based on credible information, the Kudapur Sub-division police led by ASP Hariram Shanker and team raided various clubs in Goliyangadi, Siddapur, Koteswar and Basrur where the accused were found gambling illegally.

All the clubs had taken court permission for recreation but were illegally indulging in gambling. They had also violated the court conditions and were involved in illegal gambling.

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.
News Network
February 17,2020

Bengaluru, Feb 17: Union Finance Minister Nirmala Sitharaman on Monday assured that the Centre is committed to stand by its promise of providing Rs 18,600 crore Bengaluru suburban Rail project.

Addressing a press conference after a post-budget interactive session with the representatives of the various trade bodies, industry leaders and others here, she said that the union cabinet has already given its clearance for the long-pending project.

Informing that the central government will have 20 per cent of its capital share in the project followed by another 20 per cent share from the state government, she said "beside this, the union government will stand for a sovereign guarantee for the rest of the 60 percent share, which can be raised through loans from external agencies".

Comments

Add new comment

  • Coastaldigest.com reserves the right to delete or block any comments.
  • Coastaldigset.com is not responsible for its readers’ comments.
  • Comments that are abusive, incendiary or irrelevant are strictly prohibited.
  • Please use a genuine email ID and provide your name to avoid reject.